background image

IEC09000614-1-en.vsd

IEC09000614 V1 EN

Figure 35:

ACT: Validation on demand

Validation when writing to the IED

When writing the application configuration to the IED an automatic validation is
performed. The validation is the same as the manually demanded validation. Errors
will abort the writing.

5.2 

Setting configuration and setting parameters in PST

Configuration parameters and settings parameters are changeable either from
LHMI or from PST in PCM600.

Note that the some parameters are only visible in PST and some are
only visible on LHMI.

1MRK511240-UEN B

Section 5

Protection and control engineering

670 series

51

Engineering Manual

Summary of Contents for Relion 670 series

Page 1: ...Relion Protection and Control 670 series Engineering Manual...

Page 2: ......

Page 3: ...Document ID 1MRK511240 UEN Issued February 2015 Revision B Product version 1 2 Copyright 2012 ABB All rights reserved...

Page 4: ...or disclosed only in accordance with the terms of such license Trademarks ABB and Relion are registered trademarks of the ABB Group All other brand or product names mentioned in this document may be...

Page 5: ...roduct failure would create a risk for harm to property or persons including but not limited to personal injuries or death shall be the sole responsibility of the person or entity applying the equipme...

Page 6: ...rning electrical equipment for use within specified voltage limits Low voltage directive 2006 95 EC This conformity is the result of tests conducted by ABB in accordance with the product standards EN...

Page 7: ...19 Managing projects in PCM600 23 Building a plant structure 24 IEC 61850 naming conventions to identify an IED 25 Inserting an IED 27 Setting IED IP address in the project 38 Section 5 Protection an...

Page 8: ...onditions 72 Sequence for engineering of IEC 61850 protocol 72 Exporting SCL files from PCM600 73 Exporting SCD files 74 Exporting ICD or CID files 74 Engineering of vertical and horizontal communicat...

Page 9: ...The application manual should be used to find out when and for what purpose a typical protection function could be used The manual should also be used when calculating settings The Technical Referenc...

Page 10: ...DNP3 1 1 2 About the engineering manual Use the engineering manual for instructions on how to engineer the IEDs using the different tools in PCM600 The engineering manual contains the following chapt...

Page 11: ...K 505 204 BEN Sample specification SA2005 001281 Documents related to REL670 Identity number Operator s manual 1MRK 506 313 UEN Installation and commissioning manual 1MRK 506 314 UEN Technical referen...

Page 12: ...K 505 212 BEN Documents related to RES670 Identity number Operator s manual 1MRK 511 251 UEN Installation and commissioning manual 1MRK 511 252 UEN Technical reference manual 1MRK 511 250 UEN Applicat...

Page 13: ...ision Description First issue for 670 series version 1 2 A Maintenance updates PR corrections B Maintenance updates PR corrections 1MRK511240 UEN B Section 1 Introduction 670 series 7 Engineering Manu...

Page 14: ...8...

Page 15: ...l Station level Station Communication Station bus bay IED 1 bay IED 2 bay IED n 1 bay IED n NCC GW station IED2 PCM600 tool set HSI station IED1 IEC08000101 V1 EN Figure 1 Principle structure of a mon...

Page 16: ...between the logical node data model in the IED following the structure and rules in part 7 of the IEC 61850 standard and the function blocks in an IED configuration is given in the IEC 61850 communic...

Page 17: ...iles Organizing GOOSE messages received and managing the used IO signal is done by using the Signal Matrix tool Communication engineering for the DNP3 protocol by using the Communication Management to...

Page 18: ...the tools Defining allowed activities for the user profiles to use tools in PCM600 IED user management Organizing users with their rights profile and password to read and write files of the IED Defin...

Page 19: ...T Export SCD IED WRITE IET600 Import SCD IED WRITE End End Optional can be used to add additional hardware modules Configure IED functionality Parametrization Signal engineering Create Single line dia...

Page 20: ...uration Configure the protection or control function for example for a transformer application as requested Save the configuration made with ACT to make the interfaces and signals available for other...

Page 21: ...61850 engineering See the application manual for other protocols LON SPA IEC103 The IED restarts automatically when writing an IED configuration where changes have been made to for example configurati...

Page 22: ...16...

Page 23: ...fic IED type and version is divided in two parts The IED connectivity package base module is common for all 670 series IEDs The IED specific module is separate for each type of IED Installing IED Conn...

Page 24: ...he installation Launch the Connectivity package manager from the Start menu 2 When a Connectivity package has not been activated before starting PCM600 the message box in Figure 4 is shown 3 Click Yes...

Page 25: ...sed station protocol is used PCM600 communication can use the same Ethernet port and IP address To connect PCM600 to the IED two basic variants must be considered Direct point to point link between PC...

Page 26: ...t or communication will fail It is recommended to change the IP address of the front port if the front and rear port are set to the same subnet Setting up the PC or workstation for point to point acce...

Page 27: ...5 V1 EN Figure 7 Select Network connections 2 Select Properties in the status window IEC09000356 1 en vsd IEC09000356 V1 EN Figure 8 Right click Local Area Connection and select Properties 3 Select th...

Page 28: ...address is not set to be obtained automatically by the IED see Figure 10 The IP address must be different from the IP address chosen for the IED IEC09000658 1 en vsd IEC09000658 V1 EN Figure 10 Select...

Page 29: ...ons of the exported project file is pcmp and those files are only used for exporting and importing the projects between PCM600s PCM600 uses the SQL server and the projects are stored as SQL databases...

Page 30: ...ment in the substation PCM600 has the possibility to set up a hierarchical structure of five levels for the IED identification Build up the plant structure according to the project requirements PCM600...

Page 31: ...ant structure and select New and Create from Template or Right click in the plant structure and select New General and select one of the elements IED Group or Substation Click View in the menu bar and...

Page 32: ...nical committee The technical key is shown in the Object Properties under SCL Technical Key or Technical Key The station level is predefined by AA1 where 1 is the index The voltage level is predefined...

Page 33: ...ady connected to PCM600 and the communication is established PCM600 can read the configuration directly from the physical IED This is useful when an order specific IED is used The order configuration...

Page 34: ...ing IED TR_421 in online mode and IED TR_521 in offline mode Import a template IED available in the template library as a pcmt file Import a pre configured IED available as a pcmi file Inserting an IE...

Page 35: ...D Communication protocol see Figure 16 IEC09000712 1 en vsd IEC09000712 V1 EN Figure 16 PCM600 Communication protocol selection wizard 5 Select the port and insert the IP address of the physical IED t...

Page 36: ...s been detected online by PCM600 see Figure 14 The user can not scan data from the IED or proceed further if the IED is not online or if the IP address is not correct 7 Click the Scan option to scan r...

Page 37: ...18 PCM600 IED Version detection 8 Click next to open the Housing Selection Page and select the housing and display type of the IED see Figure 19 1MRK511240 UEN B Section 4 Setting up a project 670 ser...

Page 38: ...etup Complete Page dialog shows the summary of the IED Type IED Version IP Address of IED and Order Number see Figure 20 It is possible to Cancel the insertion or confirm the configuration and do the...

Page 39: ...When the online configuration is completed it is advised to read the configuration from the IED to ensure that the IED object in PCM600 has the same configuration data as the physical IED Inserting an...

Page 40: ...o type the correct IP address in the Communication port and IP address dialog The version information needs to be selected from the drop down menu as shown in Figure 21 IEC09000741 V2 EN Figure 21 PCM...

Page 41: ...te library to create a new IED in the plant structure Change the IP address and the name that corresponds to the physical IED after a template IED has been imported A template IED can only be inserted...

Page 42: ...IED from the list of available IEDs 4 Click the icon in the right column of the list of available templates to open the Template Properties Verify the template information see Figure 24 and click Clo...

Page 43: ...window remains open until the user clicks Close Inserting a pre configuration Pre configurations in PCM600 are available as pcmi files and include all information that is related to the IED object in...

Page 44: ...he only requirement is that all needed hardware and software options are available It is possible to give the inserted IED in the plant structure a user defined name Be sure to only user characters a...

Page 45: ...ndow see Figure 27 IEC08000121 vsd IEC08000121 V1 EN Figure 27 Alternative 2 IP address via IED Object Properties window Procedure 1 Select the IED to enter the IP address 2 Open the Object Properties...

Page 46: ...he time at which the IP address is available To enter the IP address via the IED object properties window allows to changing the IP address at any time Section 4 1MRK511240 UEN B Setting up a project...

Page 47: ...ill available for 670 series in PCM600 but the user is not constrained to use them anymore The user can connect the function blocks inputs and outputs directly to the hardware channels Some function b...

Page 48: ...ion configuration They are designed for a various number of functions and organized in type groups The different function block types are shown in the Object Types View Figure 28 presents an overview...

Page 49: ...ut 9 Hardware binary output channel 10 Hardware analog input channel 11 User defined signal name 12 Hardware binary input channel 13 Execution order 14 Cycle time 15 Instance number 16 Inverted input...

Page 50: ...D and the IED is connected to PCM600 in online mode the signal value in ACT is shown as zero All not mandatory input signals have a default value that will be used when not connected 5 1 4 Function bl...

Page 51: ...o 3 8 or 100 ms Depending on function block type and the 670 series product only one two or all three possibilities may be available The combination Execution Order Instance Number is predefined by AB...

Page 52: ...flow must have the same or a higher cycle time and or execution order See Figure 31 IEC09000615 1 en vsd IEC09000615 V1 EN Figure 31 Cycle time and execution order A function block type can be define...

Page 53: ...ones in group 2 The following function blocks in group 3 must have a higher execution order than the main function block in group 2 5 1 5 Configuration parameters 5 1 6 Connections and variables A con...

Page 54: ...tion is also represented in SMT with a cross mark Hardware channels are always visible in SMT Supported hardware channels are Binary input channels Binary output channels Analog input channels A hardw...

Page 55: ...ock On demand by starting the validation When writing the application configuration into the IED Validation when creating the application configuration Validation is made when creating the application...

Page 56: ...n Errors marked by a red circle with a cross Example A mandatory input signal that is not connected Warnings will not prevent writing to the IED Errors have to be corrected before writing the applicat...

Page 57: ...the same as the manually demanded validation Errors will abort the writing 5 2 Setting configuration and setting parameters in PST Configuration parameters and settings parameters are changeable eith...

Page 58: ...iguration parameter values Setting parameter A setting parameter short form only setting is a parameter that can be changed in the IED at runtime Setting group Nearly all settings used by the IED for...

Page 59: ...nput channel is connected to several different function blocks in ACT the connection will appear as glue logic in SMT A binary output channel can only be activated from one function block output If it...

Page 60: ...Connection between binary input channels to binary input signals Depending on the IED capability SMT has a separate sheet for each possible combination The possible sheets are Binary Inputs Binary Ou...

Page 61: ...ngineering process and the required sequences IEC09000680 1 en vsd Local HMI ACT SMT Select and configure HMI function blocks PST Set LEDs END SAVE SAVE GDE ACT Create the single line diagram SAVE IEC...

Page 62: ...special function blocks is available for all the operation element groups on LHMI See the technical reference manual for more information about function blocks List of LHMI function blocks that are av...

Page 63: ...LED turns to OFF LatchedAck S F The same as LatchedAck F S but the LED starts with steady state and flashes after acknowledgment LatchedColl S The LED illuminates in all cases in steady mode only The...

Page 64: ...et S General operation definitions for the LEDs LED operation mode Follow S Activating signal LED IEC01000228_2_en vsd IEC01000228 V2 EN Figure 41 LHMI LED operation mode Follow S Monitoring a signal...

Page 65: ...acknowledgment it gets a steady light Activating signal LED Acknow en01000231 vsd IED500 IEC01000231 V1 EN Figure 42 Operating sequence 3 LatchedAck F S LED operation mode LatchedAck S F This operatio...

Page 66: ...he disturbance allows a fast overview about the disturbance To get always the situation of the last occurred disturbance the LEDs are reset after a predefined time tReset So this is the longest time a...

Page 67: ...e angles are shown as radians in the single line diagram GDE measurand symbols but in degrees in other views on the LHMI 6 2 1 Concept description to present and generate diagrams in graphical display...

Page 68: ...tool 2 GDE has a fixed symbol library window on the left side of the display 3 The presentation is empty when no page exists for the IED Display window and sequence order It is important to link corre...

Page 69: ...f the display window When changing to the other library standard GDE closes the library windows changes the symbols according to the selected new standard and redraws the single line diagram in the di...

Page 70: ...a raster of 13 x 8 columns x rows Each symbol presented by 24 x 24 pixels included by the drag and drop method must be dropped in a raster box The icon snap to grid must be enabled to place a symbol...

Page 71: ...mbols by drag and drop in a raster box 3 Click the Link icon to enable direct line drawing 4 Center the mouse pointer on the center of a connection point visible in two circles at the endpoints of a l...

Page 72: ...th east south or west Use the object property window to do it 6 Place measurements when needed 7 Edit the name unit and number of decimals of the measurements 8 Select each object that has a dynamic l...

Page 73: ...tion Switch controller of type CSWI for an apparatus All configured function blocks with measurements of type MMXU for the measurements VSGGIO for one bit indications for the dynamic text symbols SLGG...

Page 74: ...number given in the PST tree and to the application function block in ACT Only those apparatus and measurements are shown that are configured in the application configuration program en05000611 vsd IE...

Page 75: ...ere is a strict relation between the function blocks and the logical node types This relation is automatically handled by the PCM600 tools The concept in IED is such that the 61850 data for each funct...

Page 76: ...le within the logical node Whenever a function block is instantiated in ACT PCM600 automatically generates the corresponding logical node data In Figure 52 this is shown by two parts per function bloc...

Page 77: ...dataset In the opposite direction the standard only defines the IED as a receiver of the GOOSE message How the GOOSE input signals are handled must be defined in the IED application configuration The...

Page 78: ...2 IEC 61850 engineering procedure 7 2 1 IEC 61850 protocol references and pre conditions To engineer the IEC 61850 protocol interface for the IED the following additional manuals or knowledge of thei...

Page 79: ...file PCM600 1 create project import SCD file configure data sets configure Report CBs configure GOOSE CBs export SCD file IET600 2 import SCD file link GOOSE input data Write to IED PCM600 3 SCD file...

Page 80: ...627 1 en vsd IEC09000627 V1 EN Figure 56 IEC 61850 SCL Export Options 5 Select Export Private Sections and click Export to export the private sections to the SCD file A progress window shows the ongoi...

Page 81: ...tal communication in IET600 For IEC 61850 engineering a separate system configuration tool is needed to be used with PCM600 In PCM600 Ver 2 3 or earlier the recommended tool is CCT600 In PCM600 Ver 2...

Page 82: ...e report control blocks are connected to the vertical clients in the SCD file for a 670 series pre configured IED Check each IED client and configure them to the subnetwork before connecting report co...

Page 83: ...t import the SSD file part of the SCD file 4 2 Click Don t import IEDs of unknown type to protect the existing IEDs in case the SCD file does not match the original configuration in PCM600 4 3 Click R...

Page 84: ...s in SMT is required to be able to write the configuration to the IED Be sure to set the setting Operation for GOOSEBINRCV and GOOSEINTLKRCV to On in PST to enable GOOSE communication 6 Write the conf...

Page 85: ...1 Select an existing IED to import IEC 61850 files 2 Select the file type of IEC 61850 to import from the Files of type drop down list ICD or CID 3 The SCL Import Option menu opens which queries how...

Page 86: ...been completed A progress window presents the import procedure 4 IEC09000631 1 en vsd IEC09000631 V1 EN Figure 61 IEC 61850 SCL Import option 7 6 Writing communication configuration to IED IEC commun...

Page 87: ...he IED Other parts of the configuration will be updated If no change has been done to the communication configuration part select No in the Update Communication window IEC09000729 1 en vsd IEC09000729...

Page 88: ...82...

Page 89: ...function type and desired information number where an information number must be supplied for each IEC 60870 5 103 function block instance in the Parameter Setting tool 4 Set the general communication...

Page 90: ...84...

Page 91: ...t are located between the windows to move all signals or a set of individual signals between the windows DNP3 signal types index and default setting for classes are predefined in CMT Adapt the signal...

Page 92: ...for signal movement see Figure 63 IEC09000722 1 en vsd IEC09000722 V1 EN Figure 63 CMT Container window design when selecting DNP3 protocol Procedure to move signals 1 Select one or several signals C...

Page 93: ...to be saved before leaving CMT IEC08000339 vsd IEC08000339 V1 EN Figure 65 CMT Marker to indicate changes in the container 9 3 Setting DNP3 signal parameters Two parameters per signal can be set for a...

Page 94: ...nd click OK Procedure to set class configuration 1 Click in the class field of the signal to change the class configuration 2 The Select Class window opens 3 Make the selection according to the defini...

Page 95: ...he project Unsolicited reporting is possible as well Modify the organization of the classes for each signal individually Procedure 1 Click in the Class field of the signal A new window Select Class op...

Page 96: ...90...

Page 97: ...aptive signal detection AWG American Wire Gauge standard BBP Busbar protection BFP Breaker failure protection BI Binary input BIM Binary input module BOM Binary output module BOS Binary outputs status...

Page 98: ...703 over a balanced line Involves four twisted pairs two of which are used for transmitting data in both directions and two for transmitting clock signals CPU Central processor unit CR Carrier receive...

Page 99: ...e division multiplexer for the transmission of up to seven duplex channels of digital data over optical fibers G 703 Electrical and functional description for digital lines used by local telephone com...

Page 100: ...ectrical EMF Electromotive force IEEE 1686 Standard for Substation Intelligent Electronic Devices IEDs Cyber Security Capabilities IED Intelligent electronic device I GIS Intelligent gas insulated swi...

Page 101: ...ng module MVB Multifunction vehicle bus Standardized serial bus originally developed for use in trains NCC National Control Centre NUM Numerical module OCO cycle Open close open cycle OCP Overcurrent...

Page 102: ...alanced serial interface for the transmission of digital data in point to point connections RS485 Serial link according to EIA standard RS485 RTC Real time clock RTU Remote terminal unit SA Substation...

Page 103: ...he entire US Department of Defense protocol suite based upon these including Telnet FTP UDP and RDP TEF Time delayed earth fault protection function TNC connector Threaded Neill Concelman a threaded c...

Page 104: ...by the military name Zulu time Zulu in the phonetic alphabet stands for Z which stands for longitude zero UV Undervoltage WEI Weak end infeed logic VT Voltage transformer X 21 A digital signalling in...

Page 105: ...99...

Page 106: ...act us ABB AB Substation Automation Products SE 721 59 V ster s Sweden Phone 46 0 21 32 50 00 Fax 46 0 21 14 69 18 www abb com substationautomation 1MRK511240 UEN B Copyright 2012 ABB All rights reser...