Additional information
Task
Contact your local grid and MV
authority.
Make sure that all the local regulations, applicable laws, and
standard are met.
Applicable for C module MV
switchgear
Turn the earthing switch on the grid side of the MV switchgear
to the “not earthed” position.
Contact your local grid and MV
authority. Only authorized personnel
are permitted to make the connections.
Ask the power grid owner to connect the station to the power
grid. Wait until the station is connected to the power grid
before proceeding.
Applicable for C module MV
switchgear.
Turn the disconnecting switch on the grid side of the MV
switchgear to Closed position.
Applicable for V module MV
switchgear
Turn the earthing switch on the MV Transformer side of the
MV switchgear to the “not earthed” position.
Applicable for V module MV
Switchgear
Turn the disconnecting switch on the MV transformer side
of the MV switchgear to the closed position.
Applicable for V module MV
switchgear
Close the main breaker of the MV transformer.
Make sure that the voltage level on the low voltage side of
the MV transformer is correct. Adjust the MV transformer tap
settings if needed.
See MV tansformer documentation
Run the MV transformer with no load for several hours.
See MV transformer documentation
Check the MV transformer for any malfunctions. Observe
the temperature, listen to audible changes, etc.
Connecting the AC cabinet
De-energize the MV transformer.
Also de-energize (open) all other
switches, disconnectors and breakers
of the Auxiliary service board.
Close the main switch of the Auxiliary service transformer.
Energize the MV transformer.
Close the Auxiliary service transformer primary breaker.
Must be 230/400 V ±10%
Check that the Auxiliary service transformer secondary
winding voltage level is 230/400 V.
Close the Auxiliary service transformer secondary breaker.
Maintain "Closed" condition for the
auxiliary service lines with load. Only
open switches/breakers with loads.
Close the auxiliary breakers one at a time. After closing each
breaker, check the voltage values.
Inverters must be de-energized.
Close the fuse base switches of the inverter inputs one at a
time. Check each fuse base for voltage values directly in the
inverter input, before opening the next fuse base.
See inverter manual.
See inverter manual.
Follow the inverter commissioning procedure.
If any other optional equipment is integrated into the MVS such as UPS, communication
equipment and others, then check the equipment’s applicable documentation before executing
the start-up procedure.
Start-up and operation 53
12
Summary of Contents for PVS-175 Series
Page 1: ... ABB SOLAR INVERTERS PVS 175 medium voltage station Hardware manual ...
Page 2: ......
Page 4: ......
Page 8: ...8 ...
Page 14: ...14 ...
Page 26: ...26 ...
Page 32: ...32 ...
Page 40: ...6 Apply a layer of sealant around the hood border 40 Mechanical installation ...
Page 48: ...48 ...
Page 54: ...54 ...
Page 68: ...68 ...
Page 70: ......