Section 3 Installation
Installation Process
5.
Connect the cables in the specified order, according to the drawing and steps
below.
•
The operator panel must be brought to ambient temperature before it
is started up. If condensation forms, ensure that the operator panel is
dry before connecting it to the power outlet.
•
Ensure that the operator panel and the controller system have the same
electrical grounding (reference voltage level), otherwise errors in
communication may occur.
•
Ensure that the voltage and polarity of the power source is correct.
•
Separate high voltage cables from signal and supply cables.
•
Shielded communication cables are recommended.
24V DC
RS232/
RS422/
RS485
24V DC
A
D
Controller
Power
B
Ethernet
C
–
Connect cable A.
–
Connect cable B, using an M5 screw and a grounding conductor (as short
as possible), that is sized correctly according to local electrical codes.
–
Connect cable C.
–
Connect cable D. The recommended cross-section of the cable is 1.5 mm
2
..
6.
Carefully remove the protective film over the operator panel display, take care
to avoid static electricity that could damage the panel.
3BSE069462-600 Rev D
19
Summary of Contents for PP882
Page 1: ...Compact Product Suite Panel 800 Version 6 PP882 Hardware and Installation ...
Page 2: ......
Page 3: ...Panel 800 Version 6 PP882 Hardware and Installation ...
Page 6: ...6 3BSE069462 600 Rev D ...
Page 16: ...Appearance of Air in Touch Screen Section 2 Safety Precautions 16 3BSE069462 600 Rev D ...
Page 24: ...Section 4 Technical Data 24 3BSE069462 600 Rev D ...
Page 32: ...PP882 Outline Section 6 Operator Panel Drawings 32 3BSE069462 600 Rev D ...