Anchoring to the base
The enclosed dowels must be used for anchoring (6 x Hilti HKD-ER compact dowels M8x30).
Technical data
M8
Anchorage ground
Standard concrete with a strength
class of C20/25-C50/60 or greater
Recommended load
Tension N (uncracked concrete)
4
Per dowel
Transversal shear V (uncracked con-
crete)
3,9 kN
Required clearance
10,5
cm
Torque Tinst
≥
8 Nm
Drill-hole diameter do
10 mm
Drill-hole depth h1
33 mm
Specifications for compact dowels Hilti HKD-ER M8x30. Source: Hilti
Making drillholes
►
Mark the 6 holes on the concrete foundation using the baseplate of the floor-mounted
column.
Make sure that the connection cable is located precisely underneath the opening in the
baseplate.
►
Drill the 6 mounting holes:
Diameter: 10 mm
Drill-hole depth: 33 mm
►
Hammer the enclosed dowels using the Hilti HSD-G manual setting tool (not included
in the scope of delivery) so that they are flush with the floor.
Hilti HSD-G manual setting tool. Source: Hilti
Please also observe the following instructions: