88 Installation checklist
Cooling circuit
See chapter
If the converter has been stored over one year: The electrolytic DC capacitors in the DC link of the
converter have been reformed. See the reforming instructions (available from your local ABB
representative).
There is an adequately sized protective ground conductor between the generator and the converter.
The grid voltage matches the nominal input voltage of the converter.
The grid cables have been connected to appropriate terminals (incoming cubicle terminals L1, L2
and L3), the phase order is correct, and the terminals have been tightened (pull conductors to
check).
The rotor-side cables have been connected to appropriate terminals (inverter cubicle terminals U2,
V2 and W2), the phase order is correct, and the terminals have been tightened (pull conductors to
check).
The DC resistors (D150+D151) have been connected to appropriate terminals (R+ and R),
and the terminals have been tightened (pull conductors to check).
The rotor cable is routed away from other cables.
The generator cable (and DC resistor cable, if present) has been routed away from other cables.
No power factor compensation capacitors are connected to the rotor terminals.
The external control cables have been connected to appropriate plug-in terminals on the connection
board on the right-hand side of the converter.
There are no tools, foreign objects or dust from drilling inside the converter.
Shrouds are fastened and doors are closed.
The input voltage can not be connected to the U2, V2 and W2 terminals of the converter.
Ensure that the lead-throughs fulfil the requirements of degree of protection IP54 or higher.
The generator and the wind turbine are ready for start.
The cooling circuit joints are tight (modules, liquid-cooling unit etc.).
Bleed valves in all cubicles are closed (converter, liquid-cooling unit).
The external control cabling (if any) has been connected to appropriate LCU terminals.
Summary of Contents for ACS800-67LC
Page 1: ... ABB WIND TURBINE CONVERTERS ACS800 67LC wind turbine converters Hardware manual ...
Page 4: ......
Page 16: ...16 Safety instructions ...
Page 22: ...22 Introduction to the manual ...
Page 42: ...42 Operation principle and hardware description ...
Page 52: ...52 Mechanical installation ...
Page 79: ...Electrical installation 79 3 3 Rotor side cable connection terminals U2 V2 W2 ...
Page 92: ...92 Maintenance 4 6 5 5 ...
Page 103: ...Maintenance 103 Bussmann fuses Mersen fuses ...
Page 109: ...Maintenance 109 5 6 7 ...
Page 131: ...Technical data 131 Declaration of incorporation ...
Page 136: ...136 Dimension drawings ACS800 67LC 1075 0575 7 and 1375 0575 7 ...
Page 137: ...Dimension drawings 137 With 400 mm wide incoming cubicle option C111 ...
Page 138: ...138 Dimension drawings ACS800 67LC 1375 1125 7 ...
Page 139: ...Dimension drawings 139 With 400 mm wide incoming cubicle option C111 ...
Page 140: ...140 Dimension drawings ACS800 67LC 1595 0865 7 and 2035 1125 7 ...
Page 141: ...Dimension drawings 141 With 400 mm wide incoming cubicle option C111 ...
Page 143: ...Dimension drawings 143 Options 2H370 and C111 Option 1H371 ...
Page 144: ...144 Dimension drawings Options 1H371 and C111 Options 2H371 and C111 ...
Page 145: ...Dimension drawings 145 Option H378 Options H378 and C111 ...
Page 147: ...Dimension drawings 147 Option 2H372 ...
Page 148: ...148 Dimension drawings Option 3H372 ...
Page 149: ...Dimension drawings 149 Option 1H373 ...
Page 150: ...150 Dimension drawings Option 2H373 ...
Page 151: ...Dimension drawings 151 Option 3H373 ...