Starting the drive
9.6.1
Checks before starting the drive
▲
DANGER
⚠
When the drive is put into service after it has been commissioned, or after it has been taken
out of service for a longer period, use the following checklist:
9.6.2
Starting the drive remotely
When the drive is operated from remote through a higher-level control system or an operator
control desk, follow the instructions in the appropriate manuals.
9.6.3
Starting the drive locally
1. Enable the local control mode of the drive.
2. Check that no alarm or fault messages are displayed on the CDP control panel.
- If a fault message is displayed on the CDP control panel, reset the fault.
It is recommended to have the following documents at hand when starting the
drive locally for the first time after commissioning:
- “Appendix D – Wiring diagrams” to identify the circuit breakers to be
switched on
- “10 CDP control panel” on page 125 for information on functions and features of
the CDP control panel
Hazardous voltages!
- All covers must be screwed in place to prevent unintentional contact with
energized components.
1.
Tools and foreign objects are inside the cabinet.
□
2.
All auxiliary power supplies from external sources are switched on.
□
3.
All internal circuit breakers of the drive are closed.
□
4.
All covers are mounted and the doors are closed, locked or bolted.
□
5.
Grounding switch is in the ungrounded position.
□
6.
MCB is in operating position.
□
7.
No run interlocks are active.
□
LOC
RESET
REF
REM
Summary of Contents for ACS1000i air-cooled
Page 1: ... MEDIUM VOLTAGE AC DRIVES ACS1000i air cooled User manual ...
Page 3: ...Contents ACS1000i air cooled User manual ...
Page 5: ... 01 About this manual 01 5 16 ...
Page 16: ......
Page 17: ... 02 Important safety information 02 17 28 ...
Page 28: ......
Page 29: ... 03 Power electronics and cabinet features03 29 56 ...
Page 57: ... 04 Control system 04 57 70 ...
Page 71: ... 05 Transportation storage and disposal05 71 78 ...
Page 78: ......
Page 79: ... 06 Mechanical installation 06 79 88 ...
Page 88: ......
Page 89: ... 07 Electrical installation07 89 104 ...
Page 105: ... 08 Commissioning 08 105 110 ...
Page 110: ......
Page 111: ... 09 Operation 09 111 124 ...
Page 125: ... 10 CDP control panel 10 125 148 ...
Page 149: ... 11 Preventive and corrective maintenance 11 149 172 ...
Page 173: ......