background image

09/2021 

Page 11

User Manual 
Extended Battery Pack 6kVA, 10kVA

3.4. Installing the optional battery cabinet

1.  

Figure 3

 shows the connection between the UPS and the battery cabinet.

CAUTION:

A small amount of arcing may occur when connecting an EBP to the UPS. 
This is normal and will not harm personnel. Insert the EBP cable into the UPS 
battery connector quickly and firmly.

2.  Plug the EBP cable(s) into the battery connector(s) as shown in 

figure 2

Up to four EBPs may be connected to the UPS.

3.  Verify that the EBP connections are tight and adequate bend radius and 

strain relief exist for each cable.

Figure 3

Connecting the EBPS:

                                      

figure 3

Set the UPS for the number of battery packs installed.

Summary of Contents for 9885163

Page 1: ...EXTENDED BATTERY PACK User Manual 6kVA 10kVA Tower UPS Model Article number a TroniX Extended Battery Pack Pro 9885163 09 2021 Page 1...

Page 2: ...lled Read carefully before use Read this manual carefully before installation It contains important regulations and instructions for the use of this product and provides technical support for the oper...

Page 3: ...nd abbreviations used in this guide 5 3 Installation 6 3 1 Inspecting the Equipment 6 3 2 Battery installation 6 3 3 Installing and connecting the batteries 8 3 4 Installing the optional battery cabin...

Page 4: ...S is not connected to an AC supply CAUTION With batteries there is a risk of electric shock or burns due to high short circuit current Observe the appropriate safety precautions Maintenance work and r...

Page 5: ...CAUTION General warning of danger points NOTE This symbol indicates texts notes or tips Failure to take precautionary measu res may result in damage to the product and or its functions or to an object...

Page 6: ...ing please keep it for reuse or dis pose of it properly Check the accessories against the packing list and contact the dealer if any parts are missing Accessories includes a TroniX battery cabinet ope...

Page 7: ...09 2021 Page 7 User Manual Extended Battery Pack 6kVA 10kVA Remove the cover of the battery cabinet to be able to install the batteries and connect the battery cables see figure 2 figure 2...

Page 8: ...parallel for operation Each string has 20 18 16 batteries in series BAT N BAT The installations of the three voltage types are described as follows Instructions for installing and connecting 40 pieces...

Page 9: ...A Instructions for installing and connecting 36 pieces of batteries Insert the batteries one after the other from bottom to top and then connect the battery cables according to the following wiring di...

Page 10: ...top and then connect the battery cables according to the following wiring diagram Wiring diagram for the installation of 32 batteries When the installation and connection of the batteries is complete...

Page 11: ...to the UPS This is normal and will not harm personnel Insert the EBP cable into the UPS battery connector quickly and firmly 2 Plug the EBP cable s into the battery connector s as shown in figure 2 U...

Page 12: ...ecautions Keep unauthorized personnel away from batteries Batteries can present a risk of electrical shock or bum from high short circuit current Observe the following precautions 1 Remove watches rin...

Page 13: ...per disposal 4 3 Testing New Batteries To test new batteries Plug the UPS into a power outlet for 48 hours to charge the batteries Start up the UPS by pressing the start up combination button Press th...

Page 14: ...chnik Nord GmbH Verbindungsweg 23 25469 Halstenbek Hamburg GERMANY Tel 49 4101 3 76 76 0 Fax 49 4101 3 76 76 66 info akkusys de www akkusys de Other manufacturers and product ranges you will find in o...

Reviews: