PERIODIC MAINTENANCE
Please note that the periodic maintenance of the air valve is an integral part of the proper pipeline
maintenance regime; it should be maintained at least once a year in accordance with the quality and
composition of the fluid in the system.
Important: Before performing any work on the air valve, make sure that all workers on site are familiar with the
safety instructions as appear chapter of this document and with all the relevant local and general safety
instructions, standards and work regulations.
4.1.
Preparation
Releasing Pressure
Shut the isolating valve located on the riser under the air valve.
Option A:
Using two combination spanners, partially unscrew the bolts connecting the air valve to the riser in order
to release the pressure. Wait till the pressure is released.
Option B. – for air valves with Plug:
Use a ratchet box wrench to gradually release the Plug of the pressure release port, wait till the pressure
is released and then unscrew the Plug completely, remove it and drain the air valve.
The maintenance procedure of the D-060 air valve is divided into the following two separate processes:
Automatic valve
Air & Vacuum valve.