Chapter 4 Units/Components Description
There are four indicators on FGEI panel. Each gigabit electrical
interface contains two indicators: link activation indicator and link
status indicator.
1. The link activation indicator flashes when data are sent or re-
ceived.
2. The link status indicator is permanently on, when the link works
well.
FGFI
There are two Gigabit Ethernet uplink optical interfaces in
SF-2800-2GE-2SFP mode on FGFI sub card, as shown in
.
F
IGURE
26 SF-2800-2GE-2SFP S
UB
-
CARD
FGFI
There are two indicators on FGFI panel: ACT1 and ACT2. They
correspond to two gigabit optical interfaces respectively. When
the link works well, the indicator is on. When data are sent or
received, the indicator flashes.
FGFE
There are one Gigabit Ethernet uplink optical interfaces and one Gi-
gabit Ethernet uplink electrical interface in SF-2800-2GE-SFPRJ45
mode on FGFE sub card, as shown in
F
IGURE
27 SF-2800-2GE-SFPRJ45 S
UB
-
CARD
FGFE
There are three indicators on FGFE panel. The gigabit optical in-
terface contains one indicator. When the indicator is on, the Link
works well. When the indicator flashes, data are sent or received.
The gigabit electrical card contains two indicators: link activation
indicator and link status indicator.
1. The link activation indicator flashes when data are sent or re-
ceived.
2. The link status indicator is permanently on, when the link works
well.
Confidential and Proprietary Information of ZTE CORPORATION
21