Chapter 5
Cabinet Installation
The installation mode of ZXG10 iBSC cabinet falls into the base installation mode and the
feet installation mode. This chapter introduces the installation procedure of ZXG10 iBSC
cabinet.
Table of Contents
5.1 Overview of Cabinet Installation
The installation mode of ZXG10 iBSC falls into the base installation mode and the feet
installation mode.
Base installation mode is applicable when the equipment room is equipped with anti-static
floor. Users should install the adjustable base (provided by ZTE) to level the cabinet.
Feet installation mode is applicable when the equipment room has a cement floor. Use
the pressure plates to install the feet under the cabinet (with four feet).
5.1.1 Cabinet Installation Requirements
Cabinet installation requirements are set out below.
1.
The cabinet shall be installed vertically. After finishing installation, the horizontal and
vertical error shall be no more than 3 mm.
2.
The cabinet layout shall meet the requirements of engineering design. The main aisle
between cabinet rows shall align and form a straight line and the error shall not be more
than 5 mm. The adjacent cabinets shall placed one by one without any clearance. The
cabinets in one row shall be in the same plane.
3.
Choose base installation mode or feet installation mode according to the floor in
equipment room. Each fastening screw shall be fixed tightly and the outside length
(height) of the same kind of screw shall be identical.
4.
No component on cabinet shall be falling off or broken. There shall be no peeling and
bumping mark on the lacquer coat, recoat it if any. Various labels shall be complete
and clear.
5.
Take full measures for anti-earthquake requirements in cabinet installation and fixation.
5-1
SJ-20110531095035-004|2011-10-28 (R2.0)
ZTE Proprietary and Confidential
Содержание ZXG10 iBSC
Страница 8: ...II ...
Страница 167: ...Figures Figure 11 7 Step 3 of Board Unplugging 11 5 V ...
Страница 168: ...Figures This page intentionally left blank ...