PB3000 User Manual
4
Chapter 2 Product Installation
2.1 Installation Precautions
1)
Install the parking barrier on a level ground. If the ground is not solid and level, a cement base is needed
before installation.
2)
The boom can be cut, but cannot be increased. After cutting the boom length, the spring balance needs to
be set again to achieve new balance. One screw on the bottom of the spring is designed for adjusting new
balance.
3)
Do not change the wire connection inside when power on.
4)
The GND should be connected to the cabinet for secure protection.
2.2 Cable Embedding
1)
Prepare φ25 protective sleeve and cable in advance.
2)
Route cables to be connected through protective sleeves.
3)
Use a tool to open a cable tray on the ground, see figure 2-1.
Figure 2-1 Cable embedding
2.3 Cabinet Installation
Installation Procedure
1) Use Bolt Holes Dimensioning to mark the installation position of the cabinet, as shown in Figure 2-2
2) Drive four expansion bolts into the Bolt Holes Dimensioning, as shown in Figure 2-3.
3) Open the access door and install the parking barrier, as shown in Figure 2-4.
4) Install screw pads and use a wrench to tighten nuts, as shown in Figure 2-5.
The power wire is wrapped
and protected using the wire
sleeve when laid out under
the ground (the strong
current should be separated
from the weak current)
Control
room
Screw pad
Ground
Ground
Cabinet
Expansion bolt
4-M12
Base concrete
A standard power wire RVV3*1.0
A signal line RVV4*0.5