background image

P-17

P-18

Operating status

Power on checking

NO.

 

1

 2

 3
 4

 5

 6

Check content

Check and ensure the circuit breaker for the EV

 

charger is reasonably selected

Confirm that there is no short circuit between the
AC output L/N/PE of the charging

Confirm that the charging gun is not connected to

 

the vehicle

Ensure the circuit breaker is closed
The charger is powered on, and the power-on selfcheck is 
completed in about 10 seconds

After the power-on self-check is completed, observe

 

the status of the LED 

indicator.Normal standby: Green breathing light ON. 
Equipment Failure: Yellow light on /Red light on (Please find below for reference)

LED light instructions

Operating status

EV Charger

Emergency stop protection

CP signal abnormal

Poor grounding/Nature and live wire
reverse connection

Over-voltage 
Protection

Under-voltage 
Protection

Over-current

 

Protection

Temperature

 

Protection

Leakage

 

Protection

LED light

Yellow light on

Yellow & Red LED flicker
alternately (interval 1s)

Red light ON

Red light flashes (flashing once every
500MS and

 

then repeating after

waiting 2 seconds)

Red light flashes (2 flashes at 500MS 
intervals, and then repeats after
waiting for 2 seconds)

Red light flashes (interval 500MS)
Red light flashes (interval 200MS)

Red light flashes (interval 500MS

 

flashes 3 times,wait 2 seconds 
and repeat)

LED board is Offline

The yellow light is on once and then
flashes 2 times

 

intermittently (after

the yellow light is on for 1second,
it flashes 2 times and 2 seconds at an
interval of 250MS)

DLB Offline

Current abnormal

The yellow light is on once and the red
light is flashing once intermittently 
(after the yellow light is on for 1 second,
 the red light flashesonce at 250MS
intervals and repeats after 2 seconds.
The yellow light is on once and the red
light is flashing 2 times intermittently 
(after the yellow light is on for 1 second, 
the red light flashes 2 times and 2
seconds

 

at an interval of 250MS)

EV Charger

No Power

Power ON Checking

Stayby

Plug the connector without swiping RFID
 (not ready to charge) 

LED light

LED OFF

Plug the connector without swiping RFID 
(ready to charge)

Green,Yellow,Red Lights ON and OFF

Green Light ON

Streaming light runs back and forth

Streaming light runs fast back and forth

Plug the connector with RFID swiped
 (not ready to charge)

Charging

streaming light runs from 
two ends to the middle

Streaming lights from the
middle to up and down

RFID initiated without charger inserted

green light on the upper,last for 1 min

Charing without current

LED lights runs from middle to 
the end (not to the bottom).

Charging with S2 disconnected

green light all on

Содержание BCP Series

Страница 1: ...BCP Series AC EV Charger Use and lnstallation Manual Scan For More Information ...

Страница 2: ...G R E E N S M A R T ...

Страница 3: ... safety instructions Cautions Notes Specification Features P 01 P 02 P 02 P 03 P 03 Maintenance instructions Product overhaul Warranty description Safety notice Operation and maintenance risk notification Use risk notification P 20 P 20 P 21 P 21 In the box In the box P 09 Installation lnstructions Step by step installation instructions bottom entry wiring Step by step installation instructions to...

Страница 4: ...Charger The EV Charger is not user serviceable Contact us for any repairs or modification Do not touch the EV Charger s end terminals with sharp metallic objects such as wire tools or needles Read this entire mandatory document before installing or using the EV charger This device should be supervised when used around children Transporting the EV Charger handle with care Do not subject it to stron...

Страница 5: ...Charger itself Any resulting damage is excluded from New Vehicle Limited Warranty and the EV Charger Limited Warranty Do not use private power generators as a power source for charging Do not operate the EV Charger in temperatures outside its operating range of 25 to 55 That cord extension sets are not allowed to be used Notes Ensure that the EV Charger s charging cable is positioned so it will no...

Страница 6: ...t protection over temperature protection imperfect earth detection CP abnormal signal protection and type A DC 6mA for europe standard IP65 Socket IP55 protecting rate operating humidity range 0 95 for indoor and outdoor With temperature sensor build in important areas for fire protection Description Voltage and Wiring Cable Length EV Charger Dimensions Frequency Weight Current Standby Power Opera...

Страница 7: ...V charger can be wall mounted or pile mounted There are three wiring ways for the EV charger bottom entry wiring Top entry wiring and rear entry wiring You will need to install the wiring box to make top entry wiring Rated charging current can be set according to different home load conditions With lightning protection ensure personal safety RFID card or auto start charging for option ...

Страница 8: ... mounted residual current device RCD and corresponding electrical load over current protection Calculate the distance to ensure minimal voltage drop Use only copper conductors Calculate the existing electrical load to determine the maximum operating current Obtain any necessary permits from the local authority that has jurisdiction and confirm that the follow up inspection has been scheduled by an...

Страница 9: ...ortably positioned on the side of base Height Recommended height 47 in 1 2 m Maximum height indoor and outdoor 60 inches 1 5 m Minimum outdoor height 24 in 0 6 m Minimum interior height 18 inches 0 45 m P 06 Maximize wifi signal reception for models with wifi function For achieving optimal functionality the Wall Mounted Connector should be connected to the local Wi Fi network To maximize signal re...

Страница 10: ... the type of grid connection available If you are unsure of the type of connection available on the service panel please consult an electrician or contact ZJBENY for assistance L N PE 230V L1 L2 L3 230V N PE 230V L1 L2 L3 230V N PE 400V 230V 230V 230V single phase power supply For single phase EV charger a single phase wire L Neutral and earth wire must be connected The phase voltage between the L...

Страница 11: ...it comes from the ceiling use the top entry installation Note Throughout the manual conduit is used as the standard term for the protective tubing that houses the service wiring In regions where conduit is not used Europe for example a cable comprised of service wiring enclosed in a protective jacket may be substituted for conduit if allowed by local regulations Conduit openings are sized for 32 m...

Страница 12: ...arger Wire Box Mounting braket RFID Card optional M32 1 5 cable gland M6 8 Screws 8 40 Socket head screws and anchorings 8 40 Flat head screws and anchorings Position Template DLB box optional Plastic lifter Water proof cover Quantity 1 1 1 2 1 4 6 2 1 1 1 2 ...

Страница 13: ...ioning plate is 1 2 m away recommended if the EV charger is installed close to the edge of the wall the positioning plate should be more than 0 5 m away from the edge of the wall Drilling the holes according to the instruction on the Position template for different installation and wiring ways Step 2 lnstall the Mounting braket Put the 8 40 Socket head screws anchoring into the holes and use the sc...

Страница 14: ...fer to your local code for proper wire sizing appropriate for the currents in your EV Charger Wiring As the picture at left shows use the screwdriver loosing the screws on the EV charger cover Wire the cable to the according terminal Note lt is the installer s responsibility to identify whether additional grounding is required to ensure that local regulations are met Grounding must be installed at...

Страница 15: ...illing pilot holes Drilling the holes according to the instruction on the Position template for different installation and wiring ways Step 2 Fix the wire box Put the 8 40 flat head screws anchoring into the holes and use the screw driver make the 2pcs 8 40 flat head screws to fix the Wire box Mounting Template on the wall wall 0 5M 1 2M Floor Level Drill Side of wall Two points on the top and bott...

Страница 16: ...rounding must be installed at the power source and not at the cable entry to the EV Charger Note Consult with your local electrician or refer to your local code forproper wire sizing appropriate for the currents in your EV Charger As the picture at left shows use the screwdriver loosing the screws on the EV charger cover Wire the cable to the according terminal Left hole position Right hole positi...

Страница 17: ...alled close to the edge of the wall the positioning plate should be more than 0 5 m away from the edge of the wall Drilling pilot holes Step 2 Put the 8 40 socket head screws anchoring into the holes and use the screw driver make the 6pcs 8 40 Socket head screws to fix the mounting braket on the wall lnstall the Mounting braket screwdriver 8 40 Expansion bolts wall 0 5M 1 2M Floor Level Drill Side...

Страница 18: ...nsure that local regulations are met Grounding must be installed at the power sourceand not at the cable entry to the EV Charger As the picture at left shows use the screwdriver loosing the screws on the EV charger cover Wire the cable to the according terminal Note Consult with your local electrician or refer to your local code for proper wire sizing appropriate for the currents in your EV Charge...

Страница 19: ... that the power has been cut off Warning Reinstall the sealing cover and Turn on power After sealing cover fixing put the facia on and fix it on the sealing cover Recommend to install a circuit breaker 40A 2P 30MA Use a screwdriver to lightly secure the sealing cover by installing only the top screws at 1 5NM 2 0NM torque If you need to open the front cover change the internal settings please use ...

Страница 20: ...ellow light on Red light on Please find below for reference LED light instructions EV Charger No Power Power ON Checking Stayby Plug the connector without swiping RFID not ready to charge LED light LED OFF Plug the connector without swiping RFID ready to charge Green Yellow Red Lights ON and OFF Green Light ON Streaming light runs back and forth Streaming light runs fast back and forth Plug the co...

Страница 21: ...shes interval 500MS Red light flashes interval 200MS Red light flashes interval 500MS flashes 3 times wait 2 seconds and repeat LED board is Offline The yellow light is on once and then flashes 2 times intermittently after the yellow light is on for 1second it flashes 2 times and 2 seconds at an interval of 250MS DLB Offline Current abnormal The yellow light is on once and the red light is flashin...

Страница 22: ... sound Status Operating Swipe to start Swipe to quit Swipe failure Start charging Stop charging NONE Open Google Play Click Search bar Input Z BOX Z BOX Z BOX Find Z BOX APP Click Download Open APP Store Click Search bar Input Z BOX Click Download Start to use Download the APP here Z BOX Z BOX Find Z BOX APP Android IOS ...

Страница 23: ...s no high voltage in the system and then repair the charger Ensure that the emergency stop circuit breaker and other components of the product can be used under any circumstances and conduct regular tests Regularly check whether the product is damaged Warranty description The user s improper handling installation incorrect use and maintenance negligence or natural damage to the product and failure...

Страница 24: ...re is any it should be cleaned up in time othewise there is a risk of fire Use risk notification Please confirm whether the parameters of the electric vehicle and the charging equipment match before use otherwise it may cause damage to the vehicle lt is strictly forbidden to use the charger in the case of equipment failure Do not operate without authorization when the charging is abnormal lf you f...

Страница 25: ...Changjiang Rd Wenzhou Daqiao Industry Park Beibaixiang Town Yueqing Wenzhou City Zhejiang Province China 325600 VERSION 20211123 For the latest version of specification please refer to www beny com or contact to benyi zjbeny com We reserve the right to explain the terms of specification ...

Отзывы: