12 - EN
EN - 13
5 Installation procedures
5.1 Installation on the wall
≥250mm
≥1065mm
635mm
1
2
1 2
Install the unit against a wall
with a minimum mass of 200
kg/m2.
The given height is an indication. The
selected type of condensation drain
and air ducts will determine the exact
height.
Attach the mounting bracket to the
wall.
�
Make sure the openings on the
bracket are on the top;
�
Make sure the bracket is level.
Hang the unit on the mounting bracket
fixed to the wall.
�
For Zehnder ComfoPipe Plus air
ducts: use opening 1;
�
For all other air ducts: use opening
2.
3
4
5
Example ancillaries
Open the semi-transparent visor.
Pull the cable tray cover forwards.
Install the necessary ancillaries as
instructed in their associated manuals.
6
Example siphon
7
Example air duct
8
Example valve
Example grille
Install the siphon to the bottom of the
unit as instructed in the installation
section of the condensation drain.
Install the air ducts to the unit as
instructed in the installation section of
the air ducts.
Do not forget to remove the
protection covers from the
unit before installing the air
ducts.
Install the valves and grilles as
instructed in the installation section of
the valves and grilles.
9
10
11
Connect the power supply of the unit.
Install all parts back in reverse order.
Commission the unit as instructed in
the commissioning chapter.