3.8.3 Installation
of charge junction/gauge connection
of road compressor
Figure 58 - road compressor installation
1
Suction line junction (S)
2
Supply line junction (D)
S
Road compressor suction line
Ø 16 mm [0.63 in ]
D
Road compressor supply line Ø 10 mm [0.39 in]
•
Install the connections (1, Figure 58) and (2) respectively on the suction and supply lines of the
road compressor.
NOTE
Provide a syphon for the oil and connect the suction pipe to the connector of the
compressor marked with the letter "S". Pour the remaining refrigerant oil into the suction
pipe.