Evaporator and condenser water piping

The evaporator and condenser liquid heads of chiller 

have nozzles which are grooved, suitable for welding 

150 psig DWP flanges or the use of flexible couplings. 

Factory mounted flanges are optional. If welding is 

done on the nozzles, flow switches, condenser level 

sensor, and water temperature thermistors should be 

disconnected and the welding ground MUST be good 

contact located at the head to prevent current damage 

to the devices.
The nozzles and water pass arrangements are furnished 

in accordance with the job requirements. Refer to the 

Product Drawings furnished with the job. Standard 

units are designed for 150 psig DWP on the water side. 

If job requirements are for greater than 150 psig DWP, 

check the unit data plate before applying pressure to 

evaporator or condenser to determine if the chiller has 

provisions for the required DWP.
Inlet and outlet connections are identified by labels 

placed adjacent to each nozzle.

Chilled water

Foreign objects which could lodge in, or block flow 

through, the evaporator and condenser tubes must be 

kept out of the water circuit. All water piping must be 

cleaned or flushed before being connected to the chiller 

pumps, or other equipment.

Permanent strainers

, which are supplied by others, 

are required in both the evaporator and condenser wa-

ter circuits to protect the chiller and other components 

including the pumps, tower spray nozzles, chilled water 

coils and controls. The strainer must be installed in the 

entering chilled water and condenser liquid line, directly 

upstream of the chiller.
Water piping circuits should be arranged so that the 

pumps discharge through the chiller, and should be 

controlled as necessary to maintain essentially constant 

chilled and condenser water flows through the unit at 

all load conditions.
If pumps discharge through the chiller, the strainer 

may be located upstream from pumps to protect both 

pump and chiller. Piping between strainer, pump and 

chiller must be very carefully cleaned before start-up. 

If pumps are remotely installed from chiller, strainers 

should be located directly upstream of the chiller.

Condenser water circuit

For proper operation of the unit, condenser refrigerant 

pressure must be maintained above evaporator pressure. 

If operating conditions will fulfill this requirement, no at-

tempt should be made to control condenser water temper-

ature by means of automatic valves, cycling of the cool-

ing tower fan, or other means, since chillers are designed 

to function satisfactorily and efficiently when condenser 

water is allowed to seek its own temperature level at re-

duced loads and off-peak seasons of the year. However, if 

it is possible for the entering condenser water temperature 

to go below the required minimum, condenser water tem-

perature must be maintained equal to or slightly higher 

Figure 8 - 

Schematic of a typical piping arrangement

LD08529

Содержание YMC2

Страница 1: ...YMC2 Model A with OptiView Control Center Centrifugal Liquid Chillers Installation Guide Supersedes 160 78 N1 512 Form 160 78 N1 222 R 134a Issue Date February 2 2022...

Страница 2: ...erenced materials This in dividual shall also be familiar with and comply with all applicable industry and governmental standards and regulations pertaining to the task in question Safety symbols The...

Страница 3: ...rding the applicability of these documents the technician should verify whether the equipment has been modified and if current litera ture is available from the owner of the equipment prior to perform...

Страница 4: ...de 3 5 1 in Code 4 Heat exchanger mod level Nominal inside diameter in Nominal length ft Marketing tube number E A 25 14 271 B R 1 1 F C R Compressor nomenclature Gas path revision level Impeller desi...

Страница 5: ...ators 14 Neoprene isolator pads 14 Install optional spring isolators 17 Make connections 19 Piping connections 19 Refrigerant relief piping 21 Unit piping 21 Control wiring 21 Power wiring 21 Supplied...

Страница 6: ...es 3 pass nozzle arrangements 28 Figure 18 Condensers compact waterboxes 2 pass nozzle arrangements 28 Figure 19 Condensers 150 psi compact waterboxes 29 Figure 20 Evaporators marine waterboxes 1 pass...

Страница 7: ...dismantled must be field assembled under the supervision of a Johnson Controls representative but otherwise instal lation is as described in this manual Component combinations Figure 1 identifies the...

Страница 8: ...1 or 2 below use the YMC2 Unit Reassembly Manual Form 160 78 N2 in conjunction with this installation manual This manual is provided with all units that are to be field assembled The services of a Joh...

Страница 9: ...enser shell assembly 3 The variable speed drive VSD 4 Miscellaneous shipped loose items Refrigerant charges are shipped separately Arrangements with the local service office must be made to ensure ref...

Страница 10: ...r shipping separately but not skidded All conduit is left on the shells Refrigerant lines between shells are flanged and capped requiring no welding All openings the shells are closed and charged with...

Страница 11: ...line compressor motor assembly is mounted with all necessary interconnecting pip ing assembled The complete unit is factory leak tested evacuat ed and shipped charged with R 134a refrigerant The motor...

Страница 12: ...ems are shipped together Four vibration isolation pads or optional spring isolators and brackets Other shipped loose items including piping wa ter temperature controls and wiring Variable speed drive...

Страница 13: ...s When optional skids are used it may be necessary to remove the skids so riggers skates can be used under the unit end sheets to reduce overall height Each unit has four lifting holes two in each end...

Страница 14: ...nal location on the floor or mount ing pad lift the unit or shell assembly by means of an overhead lift and lower the unit to its mounting posi tion If optional shipping skids are used remove them bef...

Страница 15: ...ght 15 001 lb to 29 000 lb 6 805 kg to 13 154 kg LD12641 Unit weight up to 5 500 lb 2 494 kg LD12638 Unit weight 5 501 lb to 8 000 lb 2 495 kg to 3 628 kg LD12639 Unit weight 8 001 lb to 15 000 lb 3 6...

Страница 16: ...llation A B C D E D D D LD12642 Figure 4 Neoprene isolators Operating unit weight Dimension A Dimension B Dimension C Dimension D Dimension E 15 001 lb to 29 000 lb 6 805 kg to 13 154 kg 62 in 1575 31...

Страница 17: ...unit can be lowered onto the floor Level the unit The longitudinal alignment of the unit should be checked by placing a level on the top center of the evaporator shell under the compressor motor asse...

Страница 18: ...on A B C D E F F Figure 6 Spring isolators Operating unit weight Dimension A Dimension B Dimension C Dimension D Dimension E Dimension F Up to 35 000 lb 15 880 kg 62 in 1575 31 in 787 31 in 787 6 in 1...

Страница 19: ...ra ture control valve should be the type to open on increas ing drive coolant temperature fail closed and set for a temperature above dewpoint It can be requested as factory supplied on a chiller orde...

Страница 20: ...and condenser wa ter circuits to protect the chiller and other components including the pumps tower spray nozzles chilled water coils and controls The strainer must be installed in the entering chill...

Страница 21: ...evaporator for the purpose of quickly relieving excess pressure of the re frigerant charge to the atmosphere as a safety precau tion in case of an emergency such as fire Refrigerant relief vent pipin...

Страница 22: ...Installation Figure 9 FAA unit insulation LD03827a Bold lines and shaded components represent insulation HOT GAS LINE SIGHT GLASS CONDENSER EVAPORATOR EVAPORATOR CONDENSER LIQUID LINE HOT GAS CONNECTI...

Страница 23: ...2 02 2022 2 Figure 10 FAB unit insulation LD03827b Bold lines and shaded components represent insulation HOT GAS LINE SIGHT GLASS CONDENSER EVAPORATOR EVAPORATOR CONDENSER LIQUID LINE HOT GAS CONNECTI...

Страница 24: ...or the tube maintenance Units are furnished factory anti sweat insulated on or der at additional cost This includes all low tempera ture surfaces except the two cooler liquid heads Installation check...

Страница 25: ...in 394 14 ft 0 in 4267 NOTES 1 All dimensions are approximate Certified dimensions are available on request 2 Standard water nozzles are Schedule 40 pipe size furnished as welding stub outs with ANSI...

Страница 26: ...ft 5 in 127 1 ft 5 in 432 2 ft 3 in 686 0 ft 5 in 127 NOTE Dimensions are shown in in mm 1 pass evaporator nozzle arrangements In Out Left end Right end Right end Left end Figure 12 Evaporators compac...

Страница 27: ...are not furnished 3 One two and three pass nozzle arrangements are available only in pairs shown and for all shell codes Any pair of evaporator nozzles may be used in combination with any pair of cond...

Страница 28: ...ft 9 1 8 in 841 1 ft 5 7 8 in 454 2 ft 9 1 8 in 841 NOTE Dimensions are shown in in mm LD14008 LD14011 LD14010 LD14009 Condenser nozzle arrangements 150 psi compact waterboxes 1 pass condenser nozzle...

Страница 29: ...d face water flanged nozzles are optional add 13 mm to nozzle length Companion flanges nuts bolts and gaskets are not furnished 3 One two and three pass nozzle arrangements are available only in pairs...

Страница 30: ...45 NOTE Dimensions are shown in in mm Figure 20 Evaporators marine waterboxes 1 pass nozzle arrangements LD14012 LD14015 LD14014 Figure 22 Evaporators marine waterboxes 3 pass nozzle arrangements Figu...

Страница 31: ...zzle length Companion flanges nuts bolts and gaskets are not furnished 4 One two and three pass nozzle arrangements are available only in pairs shown and for all shell codes Any pair of evaporator noz...

Страница 32: ...in 152 1 ft 3 1 2 in 394 3 ft 10 1 2 in 1181 1 ft 5 1 2 in 445 3 ft 10 1 2 in 1181 1 ft 4 1 2 in 419 1 ft 5 1 2 in 445 3 ft 10 1 2 in 1181 1 ft 4 1 2 in 419 CA25 12 in 305 8 in 203 6 in 152 1 ft 3 1...

Страница 33: ...NSI AWWA C 606 grooves allowing the option of welding flanges or use of ANSI AWWA C 606 couplings Factory installed class 150 ANSI B16 5 round slip on forged carbon steel with 1 6 mm raised face water...

Страница 34: ...ipping weight based on Form 1 shipment Refer to product drawings for detailed weight information Table 3 Evaporator marine waterbox weights to be added to standard unit weights shown on Table 2 Evapor...

Страница 35: ...Celsius multiply by 5 9 or 0 5556 Example 10 0 F range x 0 5556 5 6 C range Table 5 SI metric conversion Measurement Multiply English unit By factor To obtain metric unit Capacity Tons refrigerant eff...

Страница 36: ...Pennsylvania USA 17349 1 800 524 1330 Subject to change without notice Printed in USA Copyright by Johnson Controls 2022 www johnsoncontrols com ALL RIGHTS RESERVED Form 160 78 N1 222 Issue Date Febru...

Отзывы: