background image

FORM 150.66-CL2 (820)

2

 

JOHNSON CONTROLS

Control Panel

Check the panel to see that it is free of foreign materials 

(wire, metal chips, or similar materials) and clean out 

if required.

Power Connections

Check that the customer power cables are connected cor-

rectly to the terminal blocks or optional circuit breaker. 

Ensure that connections of power cables within the pan-

els to the circuit breaker or terminal blocks are tight.

Grounding

Verify that the unit’s protective ground terminal(s) are 

properly connected to a suitable grounding point. Ensure 

that all unit internal ground connections are tight.

Supply Voltage

Verify that the site voltage supply corresponds to the 

unit requirement and is within limits. 

Refer to Technical 

Data Section in IOM (150.66-NM2).

PREPARATION – POWER ON

Perform the commissioning using the 

detailed checks outlined in the  

Equipment Startup Checklist as the 

commissioning procedure is carried 

out.

Apply power to the chiller. Turn ON the option panel 

circuit breaker if supplied.

The machine is now live!

Switch Settings

Ensure the chiller OFF/ON UNIT switch at the bottom 

of the keypad is OFF. Place the optional circuit breaker 

handle on the panel door to ON. The customer’s discon-

nection devices can now be set to ON.

Verify the control panel display is illuminated. 

Ensure 

the system switches under the SYSTEM SWITCHES 

Key are in the OFF position.

Compressor Heaters

Verify the compressor heaters are energized. If the ambi-

ent temperature is above 96°F (36°C) the compressor 

heaters must be on for at least 8 hours before start-up 

to ensure all refrigerant liquid is driven out of the com-

pressor and the oil. If the ambient temperature is below 

86°F (30°C), allow 24 hours.

Water System

Verify the chilled liquid system has been installed cor-

rectly, and has been commissioned with the correct di-

rection of water flow through the cooler. The inlet should 

be at the refrigerant piping connection end of the cooler. 

Purge air from the top of the cooler using the plugged 

air vent mounted on the top of the cooler body.

Flow rates and pressure drops must be within limits. 

Refer to the 

Technical Data Section of the IOM (150.66-

NM2). 

Operation outside of these limits is undesirable 

and could cause damage.

If mains power must be switched OFF for extended 

maintenance or an extended shutdown period, the com-

pressor suction, discharge and economizer service stop 

valves should be closed (clockwise). If there is a pos-

sibility of liquid freezing due to low ambient tempera-

tures, the coolers should be drained or power should be 

applied to the chiller. This will allow the cooler heater to 

protect the cooler from freezing down to –20°F. Before 

placing the unit back in service, valves should be opened 

and power must be switched on (if power is removed 

for more than 8 hours) for at least 8 hours (24 hours if 

ambient temperature is below 86°F [30°C]) before the 

unit is restarted.

Flow Switch

Verify a chilled water flow switch is correctly fitted in 

the customer’s piping on the cooler outlet, and wired into 

the control panel correctly using shielded cable.

There should be a straight run of at least 5 pipe diameters 

on either side of the flow switch. The flow switch should 

be connected to terminals 2 and 13 in the panel.

Temperature Sensor(s)

Ensure the leaving liquid temperature sensor is coated 

with heat conductive compound (Part No. 013-00890-

000) and is inserted to the bottom of the water outlet 

sensor well in the cooler. This sensor also provides some 

freeze protection and must always be fully inserted in 

the water outlet sensor well.

Отзывы: