GAS PIPING
Proper sizing of gas piping depends on the cubic feet
per hour of gas flow required, specific gravity of the gas
and the length of run. “National Fuel Gas Code” Z223.1
(in U.S.A.) or the current Gas Installation Codes CSA-
B149.1 (in Canada) should be followed in all cases
unless superseded by local codes or gas utility require-
ments. Refer to the Pipe Sizing Table 5.
The heating value of the gas may differ with locality.
The value should be checked with the local gas utility.
NOTE:
There may be a local gas utility requirement
specifying a minimum diameter for gas piping.
All units require a 1/2” pipe connection at the
entrance fitting.
GAS CONNECTION
The gas supply line can be routed through the knock-
outs located on the front of the unit or through the
opening provided in the unit's base. Refer to Figure 11
to locate these access openings. Typical supply piping
arrangements are shown in Figures 4 and 5. All
shaded items are field-supplied.
If gas supply line is routed through the unit's base
ensure that the burner assembly can be removed for
maintenance without disturbing the supply line. The
supply piping and fittings must lie below the bottom gas
manifold to avoid interference with the burner assem-
bly.
Two grommets are shipped in the blower compartment
(in parts bag taped to the blower housing) of every unit
with gas heat and should be used in the knockouts
when the gas piping penetrates the front of the unit.
After the gas supply piping has been installed, the bot-
tom opening in the unit should be sealed to prevent
water from leaking into the building.
Gas piping recommendations:
1.
A drip leg and a ground joint union must be
installed in the gas piping.
2.
When required by local codes, a manual shut-off
valve may have to be installed outside of the unit.
3.
Use wrought iron or steel pipe for all gas lines. Pipe
compound should be applied sparingly to male
threads only.
4.
All piping should be cleaned of dirt and scale by
hammering on the outside of the pipe and blowing
out the loose dirt and scale. Before initial start-up,
be sure that all of the gas lines external to the unit
have been purged of air.
5.
The gas supply should be a separate line and
installed in accordance with all safety codes as
prescribed under “Limitations”. After the gas con-
nections have been completed, open the main
shut-off valve admitting normal gas pressure to the
mains. Check all joints for leaks with soap solution
or other material suitable for the purpose.
NEVER
USE A FLAME
.
TABLE 5: GAS PIPE SIZING
1/2 in.
3/4 in.
1 in.
1-1/4 in.
10
132
278
520
1,050
20
92
190
350
730
30
73
152
285
590
40
63
130
245
500
50
56
115
215
440
60
50
105
195
400
70
46
96
180
370
80
43
90
170
350
90
40
84
160
320
100
38
79
150
305
NOMINAL IRON PIPE SIZE
LENGTH IN
FEET
Maximum capacity of pipe in cubic feet of gas per hour. (Based upon
a pressure drop of 0.3 inch water column and 0.6 specific gravity gas).
Natural gas may contain some propane. Pro-
pane, being an excellent solvent, will quickly
dissolve white lead or most standard commer-
cial compounds. Therefore, a special pipe
compound must be applied when wrought iron
or steel pipe is used. Shellac base compounds
such as Gaskolac or Stalastic, and compounds
such as Rectorseal #5, Clyde's or John Crane
may be used.