MOTO
MAN
4-1
ArcWorld IV-6200 XHD DR2C System Manual
SECTION 4
INSTALLATION
The ArcWorld IV-6200 XHD DR2C system can be installed easily in just a short
time by three workers. The more people involved (within reason), the more quickly
installation can be completed. Follow established safety procedures at all times
throughout the installation process. Failure to use safe work practices can result in
damage to the equipment and injury to the workers.
CAUTION!
Installation of the ArcWorld System is not a task for the novice. The
ArcWorld system is not fragile, but it is a highly sophisticated
robotic system. Handle components with care. Rough handling can
damage system electronic components.
4.1
Materials Required
All system hardware necessary for installing the ArcWorld IV-6200 XHD DR2C
system is included with the system. Section 4.1.1 identifies customer-supplied
items and tools required to complete installation.
4.1.1
Customer-Supplied Items
•
Gas bottles for the welding torches
•
Incoming power supply to power disconnects
•
Two earth ground cables with two earth ground stakes
•
Welding wire
•
Incoming air supply: 0.04 cmm at 620.5 kPa (1.5 scfm at 90 psi)
•
1/4-inch anchors for operator station
•
1/2-inch air line fitting for filter/regulator/lubricator (FRL)
•
Ring-tongue terminal for ground wire
4.1.2
List of Tools
•
Safety glasses
•
Face shields
•
Gloves
•
Level
•
Ratchet with 3/4- inch socket
•
Adjustable wrench set
•
Hammer drill with appropriate
concrete bits
•
Phillips and flat screwdrivers
•
Hammer
•
Socket set (standard and metric)
•
Air-impact gun with 3/4-inch
socket
•
Open-end wrench set
•
Socket-head (Allen) wrench sets
(standard and metric)
•
Stepladder
•
Forklift and/or overhead crane
•
Knife
•
Wire stripper and crimper
•
1/4-inch concrete floor anchors
•
Volt/ohm meter
•
Ring-tongue terminal