Xylem McDonnell & Miller FS4-3T Series Скачать руководство пользователя страница 4

4

INSTALLATION –

STEP 1 - Determine the Location of the Flow Switch

D

FLOW

3/4

" or 1"

PIPE

5 x D

MINIMUM

5 x D

MINIMUM

D= PIPE DIAMETER

• The flow switch 

should be located in a horizontal

section of pipe

where there is a straight horizontal run

of at least 5 pipe diameters on each side of the flo w

switch. The flow switch may be installed in a vertical

pipe if the flow is in the upward direction.

• The flow switch 

must be installed in the upright

position

as shown with arrow mark on side of casting

in the same direction as fluid will flo w.

• Some system conditions that require more than 5 pipe

diameters are high viscosity fluid and high fluid v elocity.

• The flow switch should be installed in the pump suction

piping when spring-loaded check valves and/or other

closed coupled accessories are installed in the pump

discharge piping.

STEP 2 - Connecting the Flow Switch to Pipe

a.

Apply pipe sealing compound or PTFE tape to the 

NOTE:

Do not apply sealant to first threads as this 

switch is grounded (earthed) via the pipe mounting.

FLOW

b.

Insert pipe threads into flow switch and turn 2 

or 3 times until tight.

• Place one pipe wrench on base of flo w 

switch and one wrench on connecting piping.

Tighten to following torque values.

- 47 ft•lb (64 N•m) for 3/4” pipe

- 63 ft•lb (85 N•m) for 1” pipe

• Repeat to connect pipe to opposite side of 

flow switch.

PTFE

      pipe threads.

Содержание McDonnell & Miller FS4-3T Series

Страница 1: ...flow switch do not touch the terminals Make sure flow switch electrical cover is secured before turning on electric power Failure to follow this warning could cause property damage personal injury or death California Proposition 65 warning This product contains chemicals known to the state of California to cause cancer and birth defects or other reproductive harm Previous controls should never be ...

Страница 2: ...ration LVD 73 23 EEC EMC 89 33 EEC For applications with loads between 14mA and 3 7 Amps power factors exceeding 0 65 an anticipated system switch operation rate of less than 5 times per minute and any one cycle greater than 3 sec onds on and 3 seconds off Additional suppression may be required for applica tions outside these ranges Declaration of Conformity Available on request SPECIFICATIONS Mot...

Страница 3: ...3 7 14 2 2 8 3 16 62 Maximum 8 9 33 7 8 3 31 4 63 Factory or FS4 3T3 3 4 3 4 20 Minimum 2 7 6 1 2 4 5 Maximum 4 5 17 4 1 15 5 Factory or FS4 3T1 1 1 25 Minimum 5 18 9 3 2 12 1 Maximum 11 5 43 5 11 41 6 Factory or FS4 3T2 1 1 25 Minimum 4 8 18 1 2 9 11 27 Maximum 10 1 38 2 9 4 35 6 102 Factory or FS4 3T3 1 1 25 Minimum 2 7 6 1 2 4 5 Maximum 4 5 17 4 1 15 5 Max Flow Rate gpm lpm w o Paddle Damage ca...

Страница 4: ...more than 5 pipe diameters are high viscosity fluid and high fluid v elocity The flow switch should be installed in the pump suction piping when spring loaded check valves and or other closed coupled accessories are installed in the pump discharge piping STEP 2 Connecting the Flow Switch to Pipe a Apply pipe sealing compound or PTFE tape to the NOTE Do not apply sealant to first threads as this sw...

Страница 5: ... or equipment damage electrical wiring insulation must have a rating of 167 F 75 C if the liquid s temperature exceeds 180 F 82 C To prevent electrocution when the electrical power is connected to the flow switch do not touch the terminals Make sure flow switch electrical cover is secured before turning on electric power Failure to follow this warning could cause property damage personal injury or...

Страница 6: ... be used to actuate a signal alarm or other device when no flow occurs connect the wire from that device to the N C contact Connect the Hot power supply wire to C terminal FLOW OPENS CIRCUIT FLOW CLOSES CIRCUIT COMMON 1 2 3 Flow Opens Circuit Normally closed 3 Common 1 Flow Closes Circuit 2 Normally open Common FS4 3 LINE LOAD Fig 1 HOT 3 1 2 FS4 3 LINE LOAD Fig 2 HOT 3 1 2 c Determine which switc...

Страница 7: ...to be adjusted OFF ON STEP 4 Testing SECTION 5 Adjustment ADJUSTING SCREW FLOW OPENS CIRCUIT FLOW CLOSES CIRCUIT COMMON 1 2 3 Adjustment is necessary only if required flow no flow setpoints are above factory set minimum a Turn off power Remove electric enclosure cover b Turn adjusting screw clockwise 1 8 turn to increase setpoint c Place the cover on the flow switch and turn on power d Test the op...

Страница 8: ...Inc 8200 N Austin Avenue Morton Grove Illinois 60053 Phone 847 966 3700 Fax 847 965 8379 www xyleminc com brands mcdonnellmiller McDonnell Miller is a trademark of Xylem Inc or one of its subsidiaries E July ...

Отзывы: