CAUTION:

During times of shutdown, volumetric expansion

can occur. We recommend the installation of a properly sized relief
valve on both sides of the heat exchanger.

INSTALLATION

1. Before installing this equipment, environment and service

conditions should be checked for compatibility with materials of
construction. Contact your nearest Xylem Representative if you
are not sure what the actual materials of construction are.

2. Provide valves and by-passes in the piping system so that both

the shell and tube sides may be by-passed to permit inspection
or repair.

3. Provide thermometer well and pressure gauge connections in all

piping to and from the unit and locate as near the unit as
possible.

4. Provide convenient means for frequently cleaning the unit as

suggested under “Maintenance.”

5. Provide necessary air vent cocks for units so they can be

purged to prevent or relieve vapor or gas binding of either the
tube or the shell sides.

6. Foundations must be adequate so that exchangers will not settle

and cause piping strains. Foundation bolts should be set to
allow for setting inaccuracies. In concrete footings, pipe sleeves
at least one size larger than bolt diameter slipped over the bolt
and cast in place are best for this purpose, as they allow the bolt
center to be adjusted after the foundation has set.

7. Loosen foundation bolts at one end of unit to allow free

expansion of shells. Oval holes in foundation brackets are
provided for this purpose.

8. Set exchangers level and square so that pipe connections may

be made without forcing.

9. Inspect all openings in exchanger for foreign material. Remove

all thread protectors and shipping pads just before installing. Do
not expose units to the elements with pads or other covers
removed from openings since rain water may enter the unit and
cause severe damage due to freezing.

10.Be sure the entire system is clean before starting operation to

prevent plugging of tubes with sand or refuse. The use of
strainers in settling tanks in pipe lines leading to the unit is
recommended.

11.Drain connections should not be piped to a common closed

manifold.

12.Location of the operating fluids in the heat exchanger can be a

function of the application. A few tips for the location of the
operating fluids are:
a. As a cooler, the preferred arrangement is with the hot

medium through the shell and the cooling medium through
the tubes. When the hot fluid is dirty or fouling, it is better to
put it through the tubes because they are easier to clean.
With single pass units be sure the shell inlet is on the same
end as the tube side outlet. In two pass units, the shell inlet
should be at the inlet-outlet bonnet end. It is customary for
the cooling medium to enter the lower bonnet connection,
although this can be reversed if necessary.

b. As a heater, the hot medium, usually steam or hot water,

must be in the shell. If it is steam, either of the shell
connections, or both, can be used, dependent on the actual
entering velocities.

c. For the above applications and for temperatures above

150°F, the higher temperature fluid should be circulated
through the shell side of the exchanger and precaution
should be taken to avoid shock from abrupt changes in fluid
circulation temperatures.

13.Steam hammer can cause serious damage to the tubes of any

heat exchanger. A careful consideration of the following points
before an installation is made can prevent costly repairs which
may be caused by steam hammer.
a. A vacuum breaker and/or vent, should be used in accordance

with the type of steam system installed.

b. The proper trap for the steam system installed should be

used.

c. The trap and the condensate return line to the trap should be

properly sized for the total capacity of the convertor.

d. The trap should be sized for the pressure at the trap, not the

inlet pressure to the steam controller.

e. The trap must drain into an unpressurized condensate return

system. Condensate return lines must not be run at an
elevation above the bottom of the heat exchanger. To do so
may result in a buildup of the condensate level in the heat
exchanger, which could cause water hammer and damaged
tubes.

CAUTION: 

Fluids must be gradually introduced to the unit. 

Failure to do so can cause damage to the heat exchanger.

OPERATION

1. When placing a unit in operation, open the vent connections and

start to circulate the cold medium only. Be sure that the
passages in the exchanger are entirely filled with the cold fluid
before closing the vents. The hot medium should then be
introduced gradually until all passages are filled with liquid,
close vents and slowly bring the unit up to temperature.

2. Start operation gradually. Do not admit hot fluid to the unit

suddenly when empty or cold. Do not shock unit with cold fluid
when unit is hot.

BCF HCF & SSCF Heat Exchangers Installation, Operation, and Maintenance Manual

6

Содержание BCF

Страница 1: ...Models BCF HCF SSCF Fixed Tube Sheet Heat Exchangers INSTALLER PLEASE LEAVE THIS MANUAL FOR THE OWNER S USE INSTRUCTION MANUAL...

Страница 2: ...ety 3 General safety rules 3 Safety equipment 4 Product Warranty 4 Product Description 5 General description 5 Installation 6 Installation 6 Operation 6 Startup 6 Maintenance 7 Maintenance and cleanin...

Страница 3: ...ot covered in this manual could cause death serious injury or damage to the equipment This includes any modification to the equipment or use of parts not provided by Xylem If there is a question regar...

Страница 4: ...l 3 Hazard categories can either fall under hazard levels or let specific symbols replace the ordinary hazard level symbols These are examples of other categories that can occur They fall under the or...

Страница 5: ...local sales and service representative within the warranty period The product is used only under the conditions that are described in this manual All service and repair work that is done by Xylem aut...

Страница 6: ...RAL DESCRIPTION BCF HCF SSCF heat exchangers are fixed tube heat exchangers using 1 4 3 8 and 5 8 diameter tubes BCF units use copper tubes brass shells and CI bonnets SSCF units are made of all 316 S...

Страница 7: ...edium through the shell and the cooling medium through the tubes When the hot fluid is dirty or fouling it is better to put it through the tubes because they are easier to clean With single pass units...

Страница 8: ...her excessively corroded nor insulated with scale Scrape to a bright surface 4 Inspect filters in the system to prevent foreign matter from entering the exchanger WARNING Proper precautions must be ta...

Страница 9: ...e used in the shell side of all heat exchangers with non removable tube bundles A marked increase in pressure drop and or reduction in performance usually indicates cleaning is necessary especially if...

Страница 10: ...Standard Xchange is a trademark of Xylem Inc or one of its subsidiaries 2018 Xylem Inc BCF HCF SSCF September 2018 Xylem www xylem com standardxchange...

Отзывы: