08/2012
4-87
WorkCentre 5021/5019
ADJ 1.3.1, ADJ 1.3.2
Repairs and Adjustments
Initial Issue
ADJ 1.3.1 IIT Lead Edge Registration
Purpose
To adjust the IIT scan timing in the Slow Scan direction and to correct the copy position.
CAUTION
Avoid using this procedure when performing the adjustment of the Lead Edge Registration.
This procedure should be performed only when the actual IIT Regi is not appropriate. This is
because the IIT Lead Edge Registration affects the precision of the document size detection,
etc.
NOTE: Before performing this procedure, make sure that the IOT Lead Edge Registration is
appropriate. (Refer to
ADJ 18.1.1
IOT Side/Lead Edge Registration.)
Check
1.
Place the Test Chart (499T283) on the Platen Glass correctly and make a copy in the fol-
lowing copy mode:
•
Copy Mode: 'Black'
•
Paper Size: 'A3'
•
Reduce / Enlarge: '100%'
•
No. of Copies: '2'
2.
Check that the distance between the lead edge of the 2nd copy and the reference line is
10.0 +/-1.6 mm or the same as the dimension on the Test Chart. (Figure 1)
Figure 1 j0mf40954
3.
If the value is not within the specified range, adjust it as follows:
Adjustment
1.
Enter NVM [715-050] Platen SS Registration Adjustment.
2.
Change the value.
•
Change amount for 1 step: 2 pulse
•
Increment of the value: The image moves towards the Tail Edge.
•
Decrement of the value: The image moves towards the Lead Edge.
ADJ 1.3.2 IIT Side Registration
Purpose
To adjust the IIT scan timing in the Fast Scan direction and to correct the copy position.
CAUTION
Avoid using this procedure when performing the adjustment of the Side Registration. This pro-
cedure should be performed only when the actual IIT Regi is not appropriate. This is because
the IIT Side Registration affects the precision of the document size detection, etc.
NOTE: Before performing this procedure, make sure that the IOT Lead Edge Registration is
appropriate. (Refer to
ADJ 18.1.1
IOT Side/Lead Edge Registration.)
Check
1.
Load A3 paper into Tray 1.
2.
Place the Test Chart (499T283) on the Platen Glass correctly and make a copy in the fol-
lowing copy mode:
•
Copy Mode: 'Black'
•
Paper Tray: Tray 1
•
Reduce / Enlarge: '100%'
•
No. of Copies: '2'
3.
Check that the distance between the side edge of the 2nd copy and the specified value is
10.0 +/-2.1 mm or the same as the dimension on the Test Chart. (Figure 1)
Figure 1 j0mf40955
4.
If the value is not within the specified range, adjust it as follows:
Adjustment
1.
Enter NVM [715-053] Platen FS Registration Adjustment.
2.
Change the value.
•
Change amount for 1 step: 1 dot
•
Increment of the value: The image moves towards the IN side.
•
Decrement of the value: The image moves towards the OUT side.
Содержание WorkCentre 5019
Страница 17: ...08 2012 2 6 WorkCentre 5021 5019 2 1 3 Initial Issue Status Indicator RAPs ...
Страница 19: ...08 2012 2 8 WorkCentre 5021 5019 2 2 1 1 Initial Issue Status Indicator RAPs ...
Страница 21: ...08 2012 2 10 WorkCentre 5021 5019 003 500 795 003 951 Initial Issue Status Indicator RAPs ...
Страница 23: ...08 2012 2 12 WorkCentre 5021 5019 004 345 Initial Issue Status Indicator RAPs ...
Страница 33: ...08 2012 2 22 WorkCentre 5021 5019 023 600 Initial Issue Status Indicator RAPs ...
Страница 35: ...08 2012 2 24 WorkCentre 5021 5019 024 910 911 915 024 950 951 954 Initial Issue Status Indicator RAPs ...
Страница 37: ...08 2012 2 26 WorkCentre 5021 5019 041 210 211 Initial Issue Status Indicator RAPs ...
Страница 39: ...08 2012 2 28 WorkCentre 5021 5019 042 325 614 Initial Issue Status Indicator RAPs ...
Страница 41: ...08 2012 2 30 WorkCentre 5021 5019 045 310 045 313 Initial Issue Status Indicator RAPs ...
Страница 43: ...08 2012 2 32 WorkCentre 5021 5019 061 321 061 325 Initial Issue Status Indicator RAPs ...
Страница 47: ...08 2012 2 36 WorkCentre 5021 5019 071 105 Initial Issue Status Indicator RAPs ...
Страница 51: ...08 2012 2 40 WorkCentre 5021 5019 075 135 Initial Issue Status Indicator RAPs ...
Страница 57: ...08 2012 2 46 WorkCentre 5021 5019 092 660 668 092 910 Initial Issue Status Indicator RAPs ...
Страница 59: ...08 2012 2 48 WorkCentre 5021 5019 093 312 093 912 Initial Issue Status Indicator RAPs ...
Страница 61: ...08 2012 2 50 WorkCentre 5021 5019 095 910 Initial Issue Status Indicator RAPs ...
Страница 63: ...08 2012 2 52 WorkCentre 5021 5019 116 321 116 377 Initial Issue Status Indicator RAPs ...
Страница 65: ...08 2012 2 54 WorkCentre 5021 5019 117 326 Initial Issue Status Indicator RAPs ...
Страница 67: ...08 2012 2 56 WorkCentre 5021 5019 123 314 Initial Issue Status Indicator RAPs ...
Страница 75: ...08 2012 2 64 WorkCentre 5021 5019 2 2 4 8 Initial Issue Status Indicator RAPs ...
Страница 89: ...08 2012 3 14 WorkCentre 5021 5019 IQ15 Initial Issue Image Quality ...
Страница 106: ...08 2012 4 4 WorkCentre 5021 5019 4 1 Initial Issue Disassembly Assembly and Adjustment ...
Страница 116: ...08 2012 4 14 WorkCentre 5021 5019 REP 1 6 1 Initial Issue Repairs and Adjustments ...
Страница 118: ...08 2012 4 16 WorkCentre 5021 5019 REP 2 1 1 Initial Issue Repairs and Adjustments ...
Страница 122: ...08 2012 4 20 WorkCentre 5021 5019 REP 4 1 1 Initial Issue Repairs and Adjustments ...
Страница 124: ...08 2012 4 22 WorkCentre 5021 5019 REP 6 1 1 Initial Issue Repairs and Adjustments ...
Страница 126: ...08 2012 4 24 WorkCentre 5021 5019 REP 7 1 1 Initial Issue Repairs and Adjustments ...
Страница 130: ...08 2012 4 28 WorkCentre 5021 5019 REP 8 2 1 REP 8 2 2 Initial Issue Repairs and Adjustments ...
Страница 162: ...08 2012 4 60 WorkCentre 5021 5019 REP 19 2 1 Initial Issue Repairs and Adjustments ...
Страница 190: ...08 2012 4 88 WorkCentre 5021 5019 ADJ 1 3 2 Initial Issue Repairs and Adjustments ...
Страница 192: ...08 2012 4 90 WorkCentre 5021 5019 ADJ 8 1 1 Initial Issue Repairs and Adjustments ...
Страница 198: ...08 2012 4 96 WorkCentre 5021 5019 ADJ 18 2 2 Initial Issue Repairs and Adjustments ...
Страница 209: ...08 2012 5 6 WorkCentre 5021 5019 5 1 4 5 1 5 Initial Issue Parts List ...
Страница 267: ...08 2012 5 64 WorkCentre 5021 5019 99 8 Initial Issue Parts List ...
Страница 293: ...08 2012 6 24 WorkCentre 5021 5019 6 1 28 6 1 29 Initial Issue General Procedures ...
Страница 295: ...08 2012 6 26 WorkCentre 5021 5019 6 2 1 6 2 2 Initial Issue General Procedures ...
Страница 299: ...08 2012 6 30 WorkCentre 5021 5019 6 3 1 3 Initial Issue General Procedures ...
Страница 303: ...08 2012 6 34 WorkCentre 5021 5019 6 3 2 3 Initial Issue General Procedures ...
Страница 305: ...08 2012 6 36 WorkCentre 5021 5019 6 3 3 Initial Issue General Procedures ...
Страница 317: ...08 2012 6 48 WorkCentre 5021 5019 6 3 6 Initial Issue General Procedures ...
Страница 319: ...08 2012 6 50 WorkCentre 5021 5019 6 3 7 Initial Issue General Procedures ...
Страница 325: ...08 2012 6 56 WorkCentre 5021 5019 6 3 10 Initial Issue General Procedures ...
Страница 327: ...08 2012 6 58 WorkCentre 5021 5019 6 3 11 Initial Issue General Procedures ...
Страница 331: ...08 2012 6 62 WorkCentre 5021 5019 6 3 13 Initial Issue General Procedures ...
Страница 335: ...08 2012 6 66 WorkCentre 5021 5019 6 3 14 Initial Issue General Procedures ...
Страница 337: ...08 2012 6 68 WorkCentre 5021 5019 6 3 15 Initial Issue General Procedures ...
Страница 347: ...08 2012 6 78 WorkCentre 5021 5019 6 3 17 Initial Issue General Procedures ...
Страница 353: ...08 2012 6 84 WorkCentre 5021 5019 6 3 19 Initial Issue General Procedures ...
Страница 355: ...08 2012 6 86 WorkCentre 5021 5019 6 3 20 Initial Issue General Procedures ...
Страница 358: ...08 2012 6 89 WorkCentre 5021 5019 6 4 1 3 General Procedures Initial Issue ...
Страница 359: ...08 2012 6 90 WorkCentre 5021 5019 6 4 1 3 Initial Issue General Procedures ...
Страница 377: ...08 2012 6 108 WorkCentre 5021 5019 6 4 3 Initial Issue General Procedures ...
Страница 393: ...08 2012 7 10 WorkCentre 5021 5019 7 1 2 Initial Issue Wiring Data ...
Страница 394: ...08 2012 7 11 WorkCentre 5021 5019 7 2 1 1 Wiring Data Initial Issue 7 2 1 1 ACH Figure 1 j0yg720101 ...
Страница 395: ...08 2012 7 12 WorkCentre 5021 5019 7 2 1 2 Initial Issue Wiring Data 7 2 1 2 ACN Figure 1 j0yg720102 ...
Страница 396: ...08 2012 7 13 WorkCentre 5021 5019 7 2 1 3 Wiring Data Initial Issue 7 2 1 3 2 5VDC 3 3VDC Figure 1 j0yg720103 ...
Страница 397: ...08 2012 7 14 WorkCentre 5021 5019 7 2 1 4 Initial Issue Wiring Data 7 2 1 4 5VDC 1 Figure 1 j0yg720104 ...
Страница 398: ...08 2012 7 15 WorkCentre 5021 5019 7 2 1 5 Wiring Data Initial Issue 7 2 1 5 5VDC 2 Figure 1 j0yg720105 ...
Страница 399: ...08 2012 7 16 WorkCentre 5021 5019 7 2 1 6 Initial Issue Wiring Data 7 2 1 6 5V RTN 1 Figure 1 j0yg720106 ...
Страница 400: ...08 2012 7 17 WorkCentre 5021 5019 7 2 1 7 Wiring Data Initial Issue 7 2 1 7 5V RTN 2 Figure 1 j0yg720107 ...
Страница 401: ...08 2012 7 18 WorkCentre 5021 5019 7 2 1 8 Initial Issue Wiring Data 7 2 1 8 24VDC 1 Figure 1 j0yg720108 ...
Страница 402: ...08 2012 7 19 WorkCentre 5021 5019 7 2 1 9 Wiring Data Initial Issue 7 2 1 9 24VDC 2 Figure 1 j0yg720109 ...
Страница 403: ...08 2012 7 20 WorkCentre 5021 5019 7 2 1 10 Initial Issue Wiring Data 7 2 1 10 24V RTN Figure 1 j0yg720110 ...
Страница 404: ...08 2012 7 21 WorkCentre 5021 5019 7 2 1 11 Wiring Data Initial Issue 7 2 1 11 IIT 3 3VDC 5VDC 24VDC Figure 1 j0yg720111 ...
Страница 405: ...08 2012 7 22 WorkCentre 5021 5019 7 2 1 12 Initial Issue Wiring Data 7 2 1 12 IIT 3 3V 5V 24V RTN Figure 1 j0yg720112 ...
Страница 406: ...08 2012 7 23 WorkCentre 5021 5019 7 2 56 1 Wiring Data Initial Issue 7 2 56 1 DADF 5VDC Figure 1 j0yg725601 ...
Страница 407: ...08 2012 7 24 WorkCentre 5021 5019 7 2 56 2 Initial Issue Wiring Data 7 2 56 2 DADF 5V RTN Figure 1 j0yg725602 ...
Страница 408: ...08 2012 7 25 WorkCentre 5021 5019 7 2 56 3 Wiring Data Initial Issue 7 2 56 3 DADF 24VDC Figure 1 j0yg725603 ...
Страница 409: ...08 2012 7 26 WorkCentre 5021 5019 7 2 56 4 Initial Issue Wiring Data 7 2 56 4 DADF 24V RTN Figure 1 j0yg725604 ...
Страница 415: ...08 2012 7 32 WorkCentre 5021 5019 4 5 Initial Issue Wiring Data ...
Страница 417: ...08 2012 7 34 WorkCentre 5021 5019 CH1 2 Initial Issue Wiring Data CH1 2 DC Power Generation 5VDC Figure 1 j0yg730102 ...
Страница 418: ...08 2012 7 35 WorkCentre 5021 5019 CH1 3 Wiring Data Initial Issue CH1 3 DC Power Generation 24VDC Figure 1 j0yg730103 ...
Страница 422: ...08 2012 7 39 WorkCentre 5021 5019 CH2 1 Wiring Data Initial Issue CH2 1 Control Panel Figure 1 j0yg730201 ...
Страница 423: ...08 2012 7 40 WorkCentre 5021 5019 CH2 1 Initial Issue Wiring Data ...
Страница 426: ...08 2012 7 43 WorkCentre 5021 5019 CH3 3 Wiring Data Initial Issue CH3 3 Electric Billing Figure 1 j0yg730303 ...
Страница 427: ...08 2012 7 44 WorkCentre 5021 5019 CH3 3 Initial Issue Wiring Data ...
Страница 428: ...08 2012 7 45 WorkCentre 5021 5019 CH4 1 Wiring Data Initial Issue CH4 1 Main Drive Control Figure 1 j0yg730401 ...
Страница 429: ...08 2012 7 46 WorkCentre 5021 5019 CH4 1 Initial Issue Wiring Data ...
Страница 433: ...08 2012 7 50 WorkCentre 5021 5019 CH5 4 Initial Issue Wiring Data CH5 4 Document Feeding Figure 1 j0yg730504 ...
Страница 435: ...08 2012 7 52 WorkCentre 5021 5019 CH5 6 Initial Issue Wiring Data CH5 6 Document Path Figure 1 j0yg730506 ...
Страница 436: ...08 2012 7 53 WorkCentre 5021 5019 CH5 7 Wiring Data Initial Issue CH5 7 Document Transmission Figure 1 j0yg730507 ...
Страница 437: ...08 2012 7 54 WorkCentre 5021 5019 CH5 7 Initial Issue Wiring Data ...
Страница 438: ...08 2012 7 55 WorkCentre 5021 5019 CH6 1 Wiring Data Initial Issue CH6 1 Document Illumination Figure 1 j0yg730601 ...
Страница 439: ...08 2012 7 56 WorkCentre 5021 5019 CH6 2 Initial Issue Wiring Data CH6 2 Carriage Control Figure 1 j0yg730602 ...
Страница 440: ...08 2012 7 57 WorkCentre 5021 5019 CH6 3 Wiring Data Initial Issue CH6 3 Image Input Figure 1 j0yg730603 ...
Страница 441: ...08 2012 7 58 WorkCentre 5021 5019 CH6 4 Initial Issue Wiring Data CH6 4 Laser Control Figure 1 j0yg730604 ...
Страница 442: ...08 2012 7 59 WorkCentre 5021 5019 CH7 1 Wiring Data Initial Issue CH7 1 Tray 2 Sensing 1TM Figure 1 j0yg730701 ...
Страница 443: ...08 2012 7 60 WorkCentre 5021 5019 CH7 2 Initial Issue Wiring Data CH7 2 Tray 1 Paper Stacking Figure 1 j0yg730702 ...
Страница 444: ...08 2012 7 61 WorkCentre 5021 5019 CH7 3 Wiring Data Initial Issue CH7 3 Tray 2 Paper Stacking 1TM Figure 1 j0yg730703 ...
Страница 445: ...08 2012 7 62 WorkCentre 5021 5019 CH7 4 Initial Issue Wiring Data CH7 4 MSI Paper Stacking Figure 1 j0yg730704 ...
Страница 448: ...08 2012 7 65 WorkCentre 5021 5019 CH8 3 Wiring Data Initial Issue CH8 3 Registration Figure 1 j0yg730803 ...
Страница 449: ...08 2012 7 66 WorkCentre 5021 5019 CH8 4 Initial Issue Wiring Data CH8 4 Paper Path Figure 1 j0yg730804 ...
Страница 450: ...08 2012 7 67 WorkCentre 5021 5019 CH9 1 Wiring Data Initial Issue CH9 1 Xero Life Control Figure 1 j0yg730901 ...
Страница 456: ...08 2012 7 73 WorkCentre 5021 5019 CH10 3 Wiring Data Initial Issue CH10 3 Fusing Figure 1 j0yg731003 ...