4.1
Preparing Commissioning
Prerequisite:
•
Conditions for operation must be fulfilled (Section 11.2).
Procedure:
1.
Ensure
that the Enable switch is pressed.
2.
Ensure
that the product is de-energized.
3.
Ensure
that all fuses are inserted (Figure 5).
4.
Ensure
that the motor protecting switch (-F31) is in position
I
5.
Ensure
that the sliding switch of the DC circuit breaker (-Q1) is in position
AUTO
6.
Ensure
that the AC circuit breaker (-Q2) is in position
OFF
7.
Ensure
that all cables and lines are in flawless condition.
8.
Connect
the PE conductor (Section 3.5.1.1).
9.
Connect
the supply voltage (Section 3.5.1.4).
10.
Connect
the batteries to the corresponding terminals (Section 3.5.1.3).
11.
Connect
the product to the grid (Section 3.5.1.2).
12.
Ensure
that the screws on all connections and terminals have the correct
torque.