INSTALLATION
6720818077 (2016/04) -
Greenstar Highflow CDi
ErP
23
4.5
Condensate, gas and water connections
4.5.1
Condensate connection
The condensate pump fills up and periodically discharges through the
flexible condensate pipe [8] between 200mm to 4500mm from floor
level. After this point the condensate flows, due to gravity, down the
21.5mm plastic pipe to the outlet.
▶ Fit the bayonet connector on the end of the condensate waste pipe to
the condensate pump. Push down and rotate clockwise until the
connector is locked.
▶ Route and secure the flexible condensate waste pipe [8] ensuring
that the condensate waste pipe is clipped securely either side of any
change of direction to prevent kinking or restriction.
▶ Cut off any excess pipe [8].
▶ Fit the condensate waste pipe [8] to adaptor [11] and secure with
clip [10].
▶ Connect adaptor [11] to 21.5mm plastic pipe and terminate
appropriately as described in section 3.4.
Fig. 23 Condensate connection
(See Pre-Installation section for condensate pipe work running from the
adaptor [11] to the discharge outlet).
Never terminate or discharge into any open source, including; sink,
basin, bath, shower, bidet, toilet etc.
4.5.2
Gas and water connections
▶ Ensure that the transit bung [12] has been removed from the gas and
water connections [A, B, C, D & E] on the boiler.
▶ Ensure the area is clear of debris and manoeuvre the boiler rear
wheels onto the outer rails of the mounting frame [6].
▶ Take care when moving the boiler to position the front wheels onto
the rails and align the gas/water connections and the flue.
▶ Secure boiler to mounting frame [6] with screw [13]
▶ Place the 4 larger valve sealing washers (shown shaded) onto valves
[A, B, D & E].
▶ Place the bonded washer [C] on to the gas valve.
▶ Ensure all pipe work is clean.
▶ Tighten up the flat sealing connections to secure:
[A] - CH flow (22mm).
[B] - DHW flow (22mm).
[C] - Gas inlet (22mm) (bonded washer).
[D] - Mains water inlet (22mm).
[E] - CH return (22mm).
Fig. 24 Connections
4.6
Pressure relief valve outlet
Fitting the pressure relief valve drain pipe (
figure 24):
▶ Connect a length of 15mm copper pipe [14] to the PRV drain pipe
[15].
The PRV drain pipe [15] should be at least 15mm diameter and run
down away from any electrical or other hazard.
Auto air vent:
▶ Release the auto air vent cap [16].
▶ Any external condensate pipe work should be
protected with weather resistant insulation to help
prevent freezing.
▶ The flexible pipe supplied can only be used inside the
property.
CAUTION:
ISOLATE THE MAINS GAS AND WATER
SUPPLY BEFORE STARTING ANY WORK AND OBSERVE
ALL RELEVANT SAFETY PRECAUTIONS.
Surplus water may be present due to factory testing.
Max. 4500mm
Min. 200mm
6720648665-39.1Wo
8 10
11
NOTICE:
The pressure relief valve is a safety device for
the boiler and if activated may discharge boiling water or
steam through the PRV drain pipe.
6720818077-12.1Wo
16
14
15
E
12
D
C
B
A
13
6
6
8