Sawmill Assembly
Auxiliary Bed Rail
8
8-23
1597doc111810
Sawmill Assembly
See Figure 8-23.
Use of the Shingle/Lap Siding Option requires three bed sections and
an auxiliary bed rail. For mills revision D4.00 and later, the auxiliary bed rail should be
installed near the end of the second (or middle) bed section. To install:
1.
Locate and drill four 13/32” diameter holes through the bed section tubes (two on each
side) as shown in the graphic below.
2.
Install the auxiliary bed rail using the provided 3/8-16 x 2 3/4” hex head bolts and lock
nuts.
See Figure 8-24.
For mills prior to revision D4.00, the auxiliary bed rail should be
installed near the end of the first bed section. To install:
1.
Remove the existing track bolt and nut near the end of the bed section. Assemble the
auxiliary bed rail to the existing hole and replace the track bolt and nut.
2.
Be sure the auxiliary bed rail is square to the bed and adjusted so the top of the rail is
even with the main bed rails. Clamp the auxiliary bed rail to the bed and mark the three
other hole locations.
FIG. 8-23
Auxiliary Bed Rail
3 1/2”
1” 4”
3/8-16 x 2 3/4”
Hex Head Bolt (4)
Flat Washer (4)
Lock Nut (4)
150076-4B
Drill four13/32” diameter holes
through bed section tubes to