3.13 Up/Down System
1.
Adjust the up/down chain tension as needed. Measure chain tension with the head all the
way to the top of the vertical mast. Secure the carriage with a chain at the top. Find the
chain adjusting bolt at the bottom of the mast, behind the battery box. Adjust the nuts on
the bolt until you can get about 1 1/2" (3.8 cm) total deflection in the center of the chain
with a 5 lb. (2.3 Kg) deflection force.
See Figure 3-9.
DANGER!
Always secure the cutting head with a 5/16”
chain with at least 1900 lbs. working load capacity before
adjusting the up/down chain. The cutting head may fall,
causing severe injury or death.
CAUTION!
Do not over-tension the chain. Over-tensioning
the chain may lead to early failure of the gear reducer.
2.
Check the up/down gearbox oil level. Add a synthetic gear oil such as Mobil SHC 634 as
needed. Drain and refill the gearbox
with 8 - 11 ounces of oil after the first 250 hours of
sawmill operation. Repeat every 5000 hours or every 2 years, whichever comes first.
Wood-Mizer offers replacement gear oil in 8 ounce bottles.
FIG. 3-9
Up/Down Chain
Adjustment Nuts
3H0020B
Содержание 1987 LT30
Страница 5: ...3087doc041610 v V I N LOCATIONS 1989 V I N DESCRIPTION 1989 ...
Страница 6: ......
Страница 10: ......
Страница 68: ......
Страница 110: ......