Start up
Original-Betriebsanleitung
HD1+HD2
14
•HD1-2_BAoDB_en_1407•ski
6.
The pump may now be filled with release agent (see chapter 7.2,
Maintenance Plan). We recommend using
release agent, order
no.: 0163333.
Result
The machine is now ready for operation.
Continue with the first cleaning (chapter 4.2).
4.2 Initial cleaning
Task
This machine was factory tested after assembly for perfect functioning with a
test-medium. The entire system should be flushed with cleaning solvent before
spray operation begins so that the material to be sprayed is not affected by the
test-medium.
Prerequisite
You will need:
1 open container with approx. 5 liters of solvent, hereafter called container „
A
“.
1 empty, open container for the mixture of cleaning material and test-medium,
hereafter called container „
B
“.
Do not use narrow-necked cans or barrels with bung hole.
Please, check whether the material hoses comply with the maximum working
pressure and the prescribed safety factor. They should not have any leaks,
kinks, signs of wear or bulges. The hose fittings must be securely attached and
also comply with maximum pressure.
Please wear protective clothing at all times, as solvent vapours and splashes of
solvent cannot be avoided completely.
Procedure
1.
The air tap lock must be closed.
2.
Connect the fluid hose to the injection lance.
3.
Connect the fluid hose (with the injection lance) to the fluid output on the
material pump.
4.
Turn the air regulator control screw to the left until it turns freely.
5.
Connect the inbound air connection to the compressed air line.