Страница 2: ...enance 8 Liability disclaimer 9 Contact From February 2014 this document applies to the WINAICO WSP and WST series and takes the place of all previous versions of the installation and mounting instructions for these modules No responsibility is accepted for the correctness of this information We reserve the right to technical changes The documentation in place at the time the module was manufactur...

Страница 3: ...ing instructions to hand at all times Information for operators Keep these instructions for the duration of the module s life Pay particular attention to the chapters on cleaning and maintenance and troubleshooting Before installing the solar system be sure to contact your local authorities and energy suppliers for the relevant guidelines and approval requirements You will only ensure the conditio...

Страница 4: ...ne Monocrystalline Polycrystalline Polycrystalline Area m 1 63 1 63 1 34 1 63 Weight kg 19 8 19 6 16 6 18 7 Max system voltage VDC 1 000 1 000 1 000 1 000 Max reverse current rating A 15 15 15 15 Connection type Tyco connection socket plug Tyco connection socket plug Tyco connection socket plug WINAICO connection socket plug MC4 intermateable Protection class IP 65 IP65 IP65 IP65 Fire class C C C ...

Страница 5: ...WINAICO is a trademark of Win Win Precision Technology Co Ltd www winaico com WSP P6 Blackline WST P6 ...

Страница 6: ... by the manufacturer so that the high voltage components can discharge Be sure to carefully follow the inverter manufacturer s installation instructions WINAICO modules are qualified for application class A Hazardous voltages IEC 61730 higher than 50V DC EN61730 higher than 120V DC hazardous power applications higher than 240W where general unrestricted access is anticipated Modules qualified for ...

Страница 7: ...rse current strength is 15 A 4 Transport and storage Check the shipment immediately upon delivery to ensure completeness and integrity Note any damage on the driver s consignment note and inform WINAICO in writing immediately The utmost care is required when handling the modules Take care when unpacking transporting and storing them Store the modules safely in cool and dry rooms The packaging is n...

Страница 8: ... least 15 In Central Europe a gradient of 30 is optimal Location The mounting site should be as free as possible from shade of any kind houses trees branches leaves cables antennas etc shade can significantly reduce the output of the solar modules Partial shade will also reduce the electric current yield A module is regarded as free of shade if the entire surface is free of shade throughout the ye...

Страница 9: ...ility of falling objects Secure the work area so that no other persons can be injured Keep children away from the installation site All parts of the module should be protected from mechanical loading e g caused by pressure tension torsional stress during transport and installation Ensure that the radius doesn t fall below the minimum permissible bend radius of 60 mm for cables at the connection so...

Страница 10: ... located on the rear side of the module in the upper section Figure Clamping on the short sides is not permitted Figure Reverse installation with connection socket pointing downward is not permissible Figure Observe specified clamping range The modules can be mounted to the substructure by clamping in place from the front or screwing on from behind The clamping area Example A for each fastening po...

Страница 11: ... or uneven structures can damage the module Note The middle clamps can be used as spacers between the module rows when mounting the modules To avoid any possible stresses and failure to comply with dimensions a gap should be maintained between the module rows We recommend a gap of approximately 2 cm For aesthetic reasons we recommend using black clamps for mounting our module series with black ano...

Страница 12: ...sert a suitably dimensioned protective diode into one of the two connection lines leading to this string such that these lie in the conductance direction in this string during the conventional generation of electrical energy i e so that the electrical current is able to pass through them In order to attain this it is necessary to connect the diode anode with the positive connection of this string ...

Страница 13: ...tions and connection specifications for the inverter Prior to connecting to the inverter check that each of the individual strings is de energised It is absolutely imperative that the inverter be connected to the public power supply network by a certified specialist ATTENTION High direct current voltage accrues even at low levels of radiation Never touch unprotected and cables that are in operatio...

Страница 14: ...on operation use or maintenance In addition no liability shall be borne for infringements of patent laws or other rights of third parties which result from the use of the modules unless mandated by law 9 Contact If you have any questions our WINAICO Team is available to assist you at all times WINAICO UK Ltd 7200 The Quorum Oxford Business Park North Oxford OX4 2JZ England Phone 44 0 1865 487149 F...