Wilo Drain MTS 40 Series Скачать руководство пользователя страница 9

English

Installation and operating instructions Wilo-Drain MTS 40.../MTS 40E...

9

• In the case of a stationary installation, install a non-

return valve and a stop valve with full passage cross-
section in the pressure pipe. These valves are to be 
installed above each pump for multiple pumps installa-
tions.

• “Original-Wilo-accessories” are recommended to 

guarantee perfect functioning of the pump/system.

7.1.1 Sump installation (Fig 1.)

Sump installation
Choose a suitable location

• Take into account the necessary pit depth H + X:

H: Height of fiberglass sump
X: Sand bed layer, X

min =

 8 in (200 mm)

• Take into account the position of the inflow connec-

tion, pressure outlet and ventilation connection.

• Take into account the depth of the inlet connection and 

a % fall for the inlet pipe.

Excavate the pit

• Excavate pit with a depth (H + X),

X

min =

 8 in (200 mm).

At the floor level, the pit should have a diameter which 
is 6.5 ft (2 m) larger than that of the sump. Observe the 
applicable regulations for excavation work/civil engi-
neering/construction work (slope angle, pit lining). If 
required due to the groundwater level, the pit must be 
protected using a groundwater drawdown.

• Make sand bed layer (X; non-cohesive, grain size 

0-1½ in (0-32 mm), no sharp-edged parts, minimum 
thickness Xmin = 8 in (200 mm)) and compact and level 
until a pit depth of (H) is reached.

Insert the fiberglass sump

• Prepare the inflow pipe, ventilation pipe and pressure 

outlet pipe on site.

• Insert the fiberglass sump in the pit.
• Align the inlet and pressure outlet connection to the 

pipes prepared on site.

• Check the alignment and position of the fiberglass 

sump including sump cover in relation to the surround-
ing ground level and adjust if necessary.

• Connect inflow pipe and pressure outlet pipe.

Connect the pipes.

• Connect the inlet pipe to the pit, maintaining a fall in 

the direction of the fiberglass sump.

• Connect the pressure pipe to the pressure outlet and 

make it frost-proof.

• Install and lay all pipes so that there is no tension.
• Test that it is leakproof, according to the relevant reg-

ulations.

Backfill the pit.

• Backfill the pit in layers (max. layer depth 12 in 

(300 mm)) all round with non-cohesive beds of equal 
depth (sand/grit without sharp-edged parts, grain size 
0-1½ in (0-32 mm)) and seal properly (97% simple 
Proctor compaction). Make sure that the fiberglass 
sump is vertical and avoid deformation!

During backfilling, ensure that the sump is kept in 
position and that it does not swell. If necessary, fill 
the sump with water before backfilling and compac-
tion in order to ensure this.

• If the surrounding ground is made up of cohesive mate-

rial, the top layer of the filling can be backfilled with an 
approx. 1½ ft (0.5 m) thick layer of this material and 
compacted to improve the sump‘s adaptation to the 
surroundings.

Install the pump

See point 7.1.2.
Remove coarse contaminants from the fiberglass sump.

NOTE:
The valves should not be connected directly to the 
pressure port or the pipe elbow. A device to vent the 
pump must be provided. Otherwise the air cushion 
cannot open the non-return valve.

WARNING! Risk of injury!
People may fall into the open sump and suffer seri-
ous injury. 

• Once the fiberglass sump is installed, always close it 

with a WILO sump cover that is suitable for the 
application.

• Have a WILO sump cover available when the instal-

lation work starts.

CAUTION! Risk of damage!
Incorrect installation can result in damage to the 
product.

• Please ensure that installation work is only carried 

out by qualified personnel!

• Install and check the pump station according to the 

relevant standards, e.g. DIN EN 1610 (Laying and 
checking sewage pipes and drains)!

• Observe national and regional regulations!
• Observe the installation and operating instructions 

for accessories!

NOTE:
If outdoor temperatures are persistently cold (below 
32 °F (0 °C)),  there is a risk of frost in the sump due to 
insufficient water exchange, particularly if the sump is 
not being used or is only being used occasionally.

• In this case, appropriate insulation measures must be 

taken on-site in the area above the pump cover.

• If you do not want to operate the sump at all, we recom-

mend you empty the sump and the pipe fully.

NOTE:
When using this pump, the stud bolts of the pump 
(pump feet) must be removed from beneath the pump 
housing!

Содержание Drain MTS 40 Series

Страница 1: ...US Installation and operating instructions Submersible Grinder Pumps Wilo Drain MTS 40 MTS 40E 6044785 Ed 04 2012 04 Wilo USA...

Страница 2: ...Fig 1 Simplex and Duplex Package Fiberglass Basin Fig 2 DN 40 1 Dual Guide Suspension Device X H Hmin S1 Hmin S2 S3 4 3 2 1 1 1 5 Hmin S1 Hmin S2 S3...

Страница 3: ...1 3 2 Hmin S1 Hmin S2 S3 Start capacitor Operation capacitor U1 V1 Common Black U2 Principal Brown Red Z2 Auxiliary Blue PE Green Yellow Start relay for start capacitor Switch relay 1 2 3 4 5 6 7 8 9...

Страница 4: ......

Страница 5: ...the operating instructions Symbols Signal words Information that appears directly on the product such as direction of rotation arrow identifiers for connections name plate and warning sticker must be...

Страница 6: ...ke void the manufacturer s declarations regarding safety Modifications to the product are only permissible after consultation with the manufacturer Original spare parts and accessories authorized by t...

Страница 7: ...max operating hours year MTS 40 200 h MTS 40E 2000 h Motor non immersed S2 8 min max operating time 8 minutes S3 25 2 5 min operation 7 5 min pause Motor Power connection See name plate Voltage toler...

Страница 8: ...ng a pipe elbow with DN 40 flange connection The motors are equipped with a thermal winding con tact which automatically switches the motor off upon overheating Monitoring is self switching on single...

Страница 9: ...ant reg ulations Backfill the pit Backfill the pit in layers max layer depth 12 in 300 mm all round with non cohesive beds of equal depth sand grit without sharp edged parts grain size 0 1 in 0 32 mm...

Страница 10: ...positionautomaticallyandsealsthepressureconnection on the foot elbow through its dead weight Fix the chain on the guide pipe bracket with shackle provide on site 7 1 3 Portable wet well installation...

Страница 11: ...is switched parallel to the operating capac itor for approx 1 second After this time has elapsed the starting capacitor is isolated from the operating capacitor 8 Commissioning 8 1 Rotation direction...

Страница 12: ...s of the macerator Rinse out the pump housing via the pressure port until no more contamination comes out of the intake chan nels of the macerator Check the cutting gap of the macerator visually check...

Страница 13: ...es Pump does not start Interruption to the main supply short circuit Insulation error in the motor winding Check mains voltage Have the cable and motor checked by a con sultant Fuses capacitor defect...

Страница 14: ...WILO USA LLC W66 N1253 Forward Way Cedarburg WI 53012 USA Phone 262 204 6600 WILO Canada Inc Bay 7 2915 10th Ave N E Calgary Alberta T2A 5L4 CANADA Phone 866 945 6236 WILO CDN FAX 403 277 9456...