Weil-McLain LGB LGB-23 Скачать руководство пользователя страница 10

10

LGB-6 to LGB-23

Series 2 – Control Supplement

Part Number 550-141-916/0304

V

Verification testing

Before starting boiler for the first time and at least annually (during annual inspection and
start-up), follow the procedures below to verify boiler controls are operating correctly and
that automatic gas valve properly shuts off gas flow. Failure to verify boiler operation
could result in severe personal injury, death or substantial property damage.

Replace any defective components. Do not attempt to operate boiler or leave boiler in
operation if any component is found to be defective or to operate incorrectly. Failure to
comply could result in severe personal injury, death, or substantial property damage.

Leak test automatic

gas valve

1. Close manual test firing valve.
2. Open the service valve and gas hand valve.
3. Install a hose barb into a pressure tap downstream of the first automatic gas valve.

Allow any accumulated gas in the line to vent off. Then connect a U-tube manometer.
If the valve seals properly, there should be no gas pressure present. Remove manometer
and hose barb and replace pipe plug in pressure tap.

4. Connect the manometer downstream of the second automatic gas valve. Temporarily

remove the power leads to the first automatic gas valve. Then connect 24 volt power to
the first automatic gas valve terminals to open it. If the second valve seals properly,
there should be no pressure at the manometer.

5. Remove the temporary power supply to the automatic gas valve. Reconnect its power

leads. Remove the manometer and plug any open pressure taps.

6. Follow Operating Instructions to place boiler in service.

Verify boiler control

sequence

1. Follow the Operating Instructions in this Supplement to start the boiler, but 

do not

open the manual test firing valve

. Open all other manual gas valves as instructed.

Leave the manual test firing valve closed.

2. The automatic pilot burner should light.
3. After the pilot lights, the boiler controls should activate the automatic gas valves. Use a

voltmeter to verify voltage to automatic valves.

4. With no gas flow to the manifold, the boiler ignition controls should turn off the

automatic gas valves after main flame ignition trial. Use a voltmeter to verify voltage to
automatic valves is turned off.

Manual test firing

valve

This boiler is equipped with a manual test firing valve — the manual gas valve piped
between the gas manifold and the first automatic gas valve in the gas train. Closing the
manual test firing valve allows verification of proper boiler operation without allowing
gas flow to the manifold and allows leak testing of the automatic gas valves. Follow the
procedures below.

Содержание LGB LGB-23

Страница 1: ...LGB LGB LGB LGB LGB 6 6 6 6 6 to to to to to LGB LGB LGB LGB LGB 23 23 23 23 23 Series 2 Natural gas Gas fired boiler Indicates presence of hazards that can cause severe personal injury death or subst...

Страница 2: ...o 2 No 1 No 2 No 1 No 2 LGB 6 2 9 LGB 15 2 16 13 27 LGB 7 2 11 LGB 16 2 18 15 29 LGB 8 2 13 LGB 17 2 18 15 31 LGB 9 2 15 LGB 18 2 20 16 33 LGB 10 2 16 LGB 19 2 20 16 34 LGB 11 2 16 LGB 20 2 22 16 36 L...

Страница 3: ...UniversalControlSystem Naturalgas Part Number 550 141 916 0304 3 Figure 1 Pilot burner assembly typical Figure 2 Main flame sensor assembly I Installation continued...

Страница 4: ...here local utility requires extend drip leg to floor 7 Install ground joint union when required for servicing 8 Support piping by hangers not by boiler or its accessories 9 Purge all air from supply p...

Страница 5: ...o the boiler must be No 14 gauge or heavier Install in conduit 5 A separate electrical circuit with a fused disconnect switch 15 amp recommended should be used for the boiler On failure to sense pilot...

Страница 6: ...6 LGB 6 to LGB 23 Series 2 Control Supplement Part Number 550 141 916 0304 III Wiring continued...

Страница 7: ...UniversalControlSystem Naturalgas Part Number 550 141 916 0304 7 Figure 3 Wiring diagram...

Страница 8: ...tion control panel and left jacket panel Mount wire support clip using sheet metal screw furnished 5 Complete wiring per wiring diagram Figure 3 pages 6 and 7 Figure 4 Junction box assembly dual base...

Страница 9: ...UniversalControlSystem Naturalgas Part Number 550 141 916 0304 9 IV Operating instructions...

Страница 10: ...ads to the first automatic gas valve Then connect 24 volt power to the first automatic gas valve terminals to open it If the second valve seals properly there should be no pressure at the manometer 5...

Страница 11: ...UniversalControlSystem Naturalgas Part Number 550 141 916 0304 11 Figure 5 Parts drawing VI Parts list continued...

Страница 12: ...12 LGB 6 to LGB 23 Series 2 Control Supplement Part Number 550 141 916 0304 Weil McLain 500 Blaine Street Michigan City IN 46360 2388 http www weil mclain com...