Part number 550-143-010/1021
43
GV90+
series
2
gas-fired water boiler – boiler manual
Allowable vent/air pipe materials &
lengths
Use only the vent materials and kits
listed in
. Provide pipe
adapters if specified.
Locate the terminations such that the total air piping
and vent piping from the boiler to the termination
will not exceed the maximum length given in
Determine termination location
1. The air and vent terminations must be installed as
shown in
2. The terminations must comply with clearances and
limitations shown in
3. Locate the terminations so they are not likely to be
damaged by foreign objects, such as stones or balls,
or subject to buildup of leaves or sediment.
Multiple vent/air terminations
)
1. When terminating multiple GV90+ boilers,
terminate each vent/air connection as described
in this section.
Terminate all vent pipes at the same height
and all air pipes at the same height to
avoid possibility of severe personal injury,
death or substantial property damage.
2. Place roof penetrations to obtain minimum clear-
ance of 12 inches between edge of air intake elbow
and adjacent vent pipe of another boiler for U. S.
installations (see
). For Canadian
installations, provide clearances required by CSA
B149.1 Natural Gas and Propane Installation Code.
or B149.2 Installation Code.
3. The air inlet of a GV90+ boiler is part of a direct
vent connection. It is not classified as a forced air
intake with regard to spacing from adjacent boiler
vents.
Prepare roof penetrations
1. Air pipe penetration:
a. Cut a hole for the air pipe. Size the air pipe
hole as close as desired to the air pipe outside
diameter.
2. Vent pipe penetration:
a. Cut a hole for the vent pipe. For either combus-
tible or noncombustible construction, size the
vent pipe hole at least 0.4” larger than the vent
pipe diameter (4” hole for 3” pipe).
b. Insert a galvanized metal thimble in the vent
pipe hole.
Figure 53
Separate pipes vertical termination
Step 1
Read and follow all instructions in this manual.
DO NOT proceed
with vent/air installation until you have read
through
Step 2
Install the boiler in a location that allows proper routing of all vent
and air piping to the selected sidewall location.
Step 3
Make sure the selected vertical termination location complies with
. (Multiple boiler terminations must also comply
.)
Step 4
Use only the vent materials listed in
. Provide pipe
adapters where required. Vent piping and air piping lengths must not
exceed the values shown in
.
Step 5
Prepare the vertical penetrations and secure penetration components
as instructed in this section. See
“Prepare roof penetrations” on page 43
“Termination and fittings” on page 44
.
Step 6
The air piping must terminate in a 180-degree return bend or
down-
turned elbow
as shown above. The vent piping must terminate in a
coupling pointed upward
as shown above.
Step 7
Install vent and air piping between the boiler and the vertical termina-
tions. Slope horizontal piping downward toward the boiler at least 1/4
inch per foot. Install pipe supports every 5 feet on both the horizontal
and vertical runs. Install a hanger support within 6 inches of any upturn
in the piping. See
for general guidelines.
Step 8
Insert the vent and air piping through the vertical penetrations and
secure the termination fittings.
Step 9
Maintain clearances shown above. Vent and air terminations must be
fitted with a bird screen as shown.
DIRECT VENT —
Vertical with separate pipes