DO NOT install the system outdoors. Keep system away from moisture, rain, and direct
sunlight. Ambient air temperature must remain below 122°F and relative humidity must
remain below 95%.
•
The system MUST be installed in accordance with all applicable national, state and local
codes.
•
Additional pretreatment may be necessary so that the feedwater conforms to the Feed
Water Specifications.
•
The skid can be bolted down to the floor, if required.
3.3.
Plumbing and UV Connections
It is the responsibility of the end user to ensure that the installation is done according to local
codes and regulations. 2” slip-on PVC flanges in inlet and outlet provides the options for both
flange and slip connections.
1. Turn off water heater(s).
2. Turn off the main water supply valve to the pipe the system will be installed in.
3. Relieve pressure within plumbing system by opening then closing both the hot and cold
sides of a faucet until water ceases to dispense from faucet.
4. If equipped with isolation valves, isolate the water heater(s) by closing its inlet and outlet
valves.
5. Connect the feed water line to the inlet side of the skid. If no isolation valve exists, it is
recommended to install an isolation valve located within 10 feet of the system.
6. Connect the outlet of the skid to treated water line plumbing. If no isolation valve exists, it
is recommended to install an isolation valve within 10 feet of the system.
WARNINGS!
Use gloves for quartz sleeve and UV lamp handling and installation. DO NOT touch the lamp
and quartz sleeve with bare hands. In cases that the lamp and sleeve are touched with bare
hands, use alcohol to clean them prior to installation.
7. Once the skid is installed and there will be no relocation, fully insert the quartz sleeve into
the reactor chamber of Lync UV system and install the O-ring over the quartz sleeve.
Press the O-ring down over the quartz sleeve until it is seated in the bevel of the stainless
steel reactor chamber's threaded port.
8. Install the quartz sleeve O-ring onto the visible end of the quartz sleeve. Screw the quartz
sleeve nut onto the quartz sleeve port thread and tighten hand tight.
9. Insert the UV lamp into the quartz sleeve. Gently press down on the glow cap and rotate
it clockwise until it locks in place on the mounting bracket.
10. Connect the lamp lead wire to the lamp.
11. Verify that outlet isolation valve(s) on skid is in close position.
12. Slowly turn on the main water supply valve.
13. Slowly open the inlet isolation valve on the skid and check for leaks and repair as needed.
14. If leaks occur at cartridge filter, close the inlet isolation valve on the skid, release pressure
by pressing pressure release button, remove lid and check the O-ring to be sure it is
properly seated.