STEP 8

Opening Speed Flow Control Adjustment: The Opening speed 
needle valve restricts flow out of the cover of the main valve. 

If recovery of pressure is slow upon increased downstream 
demand, turn the adjustment screw OUT, counterclockwise, 
increasing the rate of opening (See Figure 4B). 

If recovery of downstream pressure is too quick, as indicated 
in a rapid increase in pressure, possibly higher than the desired 
setpoint, turn the adjustment screw IN, clockwise, decreasing the 
rate of opening (See Figure 4A).

Setting the Altitude Pilot

STEP 6

Slowly open the downstream isolation valve.

STEP 7

If the valve remains closed as indicated by the stem position in 
the position indicator (See Figure 2) and the tank level is known 
to be below the desired level, SLOWLY turn the adjustment screw 
IN, clockwise, by ¼ to ½ turn increments (See Figure 3).

This will cause the valve to start opening, filling the tank. 
Additional clockwise adjustment may be necessary to raise the 
level to the overflow line.

4          IOM-ACV-127-31_6127-31 2115 

EDP# 1917063 

© 2021 Watts

IOM-ACV-127-31_6127-31 2115 

EDP# 1917063 

© 2021 Watts         5

Counterclockwise to INCREASE 

the rate of opening

Clockwise to DECREASE 

rate of opening

4A

4B

Figure 4 

Flow Control

Clockwise to INCREASE 

minimum tank level set 

point.

Figure 3 

Model 27 - Altitude Pilot

Figure 2 

Position Indicator Stem in UP Position 

Indicating Valve OPEN

Содержание LFM127-31

Страница 1: ... 2 Setting the Altitude Controls 3 Maintenance Schedule 6 Trouble Shooting Guide 6 Valve Disassembly Instructions 8 ACV Schematic 11 Local building or plumbing codes may require modifica tions to the information provided You are required to consult the local building and plumbing codes prior to installation If the information provided here is not consistent with local building or plumbing codes th...

Страница 2: ...hat proper procedures be followed Time must be allowed for the valve to react to adjustments and the system to stabilize The objective is to bring the valve into service in a controlled manner to protect the system from damaging over pressure installed sensing line and directs pressure into and out of the cover chamber of the 3 way Accelerator Pilot When the cover of the Accelerator Pilot is press...

Страница 3: ...d air will need to be bled off the valve cover during startup The ACV includes a bleed valve use a flat head screwdriver to slowly open the valve See Figure 1 STEP 4 Pressure the line by opening the upstream isolation valve slowly Air is vented through the air bleed valve Tighten the fitting when liquid begins to vent See Figure 1 Repeat the process until no air is trapped in the system STEP 5 Swi...

Страница 4: ... the downstream isolation valve STEP 7 If the valve remains closed as indicated by the stem position in the position indicator See Figure 2 and the tank level is known to be below the desired level SLOWLY turn the adjustment screw IN clockwise by to turn increments See Figure 3 This will cause the valve to start opening filling the tank Additional clockwise adjustment may be necessary to raise the...

Страница 5: ...may be turned OUT counter clockwise an additional to turn This will lower the shut off level slightly below the tank over flow mark eliminating any wave action discharge from the over flow pipe See Figure 5 STEP 10 Closing Speed Control Adjustment The closing speed needle valve regulates fluid pressure into the main valve cover chamber controlling the valve closing speed If the downstream pressure...

Страница 6: ... specification sheets for approximate cover capacity A continuous flow of water from the open port indicates a damaged diaphragm or loose disc diaphragm assembly Disassemble valve and replace diaphragm or tighten disc diaphragm assembly Test 2 Seat Seal Test 1 Close downstream isolation valve and install pressure gauges on an open inlet and outlet port of main valve 2 Open upstream isolation valve...

Страница 7: ...tion valves ensure open Diaphragm is damaged Conduct diaphragm seal test repair and replace if necessary Main valve stem assembly corroded damaged Inspect stem assembly clean replace if necessary Blockage in main valve Perform freedom of movement test if valve does not close disassemble and remove blockage Worn damaged valve seat Perform seat sealing check disassemble and inspect re pair seat if r...

Страница 8: ...Remove cover nuts and washers 3 Remove the cover If cover is not free to be removed loosen it by tapping upward along its outside edge with a dull cold chisel pic tured above a Large valves may require the installation of lifting eye bolts in order to facilitate cover removal installation ports are provided on the cover for this purpose 4 Remove the Disc and Diaphragm Assembly from the valve body ...

Страница 9: ...brush or by using a Mineral Dissolving Solution Inspect parts for wear and replace if necessary 7 Inspect valve seat If seat is not damaged removal is not necessary Valve seats 6 and smaller are threaded into the body of the valve and require a seat removal tool Figure 6 Table 1 details the tool dimensions for seat removal Valve seats 8 and larger are held in the valve body with stainless steel ca...

Страница 10: ...Nuts in a crossing pattern to ensure even distribution Test the Disc and Diaphragm Assembly for smooth travel by following the Freedom of Movement Test procedure in previous section 11 Test the integrity of the Seat Seal by following the Seat Seal Test procedure in previous section 12 Return valve to service by following instructions on the Technical Bulletin matching the valve function Size in 11...

Страница 11: ...eel 9 Stem Washer ASTM A276 304 Stainless Steel 10 Diaphragm Washer ASTM A536 65 45 12 Epoxy Coated Ductile Iron 11 Diaphragm Buna N Nitrile 12 Disc Retainer ASTM A536 65 45 12 Epoxy Coated Ductile Iron 13 Seat Disc Buna N Nitrile 14 Spacer Washer x5 NY300 Fiber 15 Disc Guide ASTM A743 CF8M 316 Stainless Steel 16 Shaft ASTM A276 304 Stainless Steel 17 Seat Ring ASTM A743 CF8M 316 Stainless Steel 1...

Страница 12: ...not be responsible for any incidental special or consequential damages including without limitation lost profits or the cost of repairing or replacing other property which is damaged if this product does not work properly other costs resulting from labor charges delays vandalism negligence fouling caused by foreign material damage from adverse water conditions chemical or any other circumstances o...