background image

C24EA3 & C24EA5 STEAMERS

Operator’s Startup, Shutdown, & Routine 

Inspection Checklist

BEFORE DAILY OPERATION

Check to make sure main water supply is turned on.                   
Verify unit is plugged in and power is turned on to the unit.

Set timer for 5 minutes.

Turn the unit on with the power switch, power light will illuminate. 

Unit will fill with water.

Timer

Close the door and in approximately 10 minutes the 

buzzer will sound indicating the unit is preheated and 

Cook/Ready Lights

ready to cook.

OnOff Switch

AFTER DAILY USE

Prior to cleaning close the door and set timers to 5 minutes.  This will loosen any stuck foods in the cooking compartment.
Turn unit off using main power switch.  Do not remove power from unit for 5 minutes to allow unit to completely drain. 

(Note: Some hood systems remove power from steamer when turned off.)

DAILY CLEANING

Thoroughly clean the unit with mild soap and water and dry.  Do not use cleaners containing chlorides or chlorine.
Thoroughly clean cavity drain screens.  Clogged drain screens can effect cooking performance, cause door leaks, and damage the unit.
Leave doors open after cleaning to allow cavity and door seal to air dry.

EXTENDED SHUT DOWN

It is recommended to perform delime on the steamer if it has not been done recently. 

Always replace filter(s) when the steamer is brought back into service.
Perform daily shut down and cleaning.
After unit has completely drained disconnect power from unit.
Shut off main water supply.

PERIODIC MAINTENANCE 

Delime generator weekly if no water treatment other than a carbon block is being used. 14 0z of ScaleRelease is required.  

ScaleRelease P/N 854893-13 (14 oz).
Change carbon block filter every 6 months or per filter manufacture’s recommendation.
Weekly inspect door seals for cuts, tears, or leaks.  Replace as needed.
Weekly check filter system pressure, 20PSI minimum / 60PSI Maximum while filling.

Change cartridge(s) if pressure is low or if they are due for replacement.

Hardness 

(Grains)

Generator 

Deliming Schedule 

with ScaleRelease

Drain Deliming 

Schedule with 

White Vinegar

0 to 5

6 Months

6 Months

5 to 10

3 Months

3 Months

10 to 15

Monthly

Monthly

15 to 20

2 Weeks

2 Weeks

20+

Other Water 

Treatment Is 

Required

Weekly

If ScaleBlocker ® SMF600 water treatment system is 

used the preventative maintenance must be performed 

every 6 months. (Kit P/N 857487-00600)  Additional 

deliming may be needed, see chart at right.  Use 

ScaleRelease (14 oz bag) P/N 854893-13 for deliming.  

One 14 oz bag is required for C24EA3 & C24EA5 

steamers.

The cooling water supplied to the steamer is not treated.  

White vinegar poured down the cavity drains will prevent 

scale from forming in the drain system. Pour one cup (8 

oz) of vinegar down each cavity drain at the end of the 

day 15 minutes after the unit has been turned off.