4.5 - GREEN MACHINE
™
- North America - Installation, Operation, Maintenance, & Troubleshooting Manual
Chapter 7: Maintenance Procedures
Page 114
7.8
Separator Check Procedure
7.8.1
Safety
Use lockout / tagout procedures prior to starting work.
7.8.2
7.7.1 Removing and Inspecting the Separator
See Figure 7-18.
1.
Turn OFF power to the VST Control Panel at the Power Switch located on the front of the VST
Control Panel. (The power, ground, and neutral will be completely disconnected from the
GREEN MACHINE
).
2.
Follow lockout-tagout procedures prior to starting work.
3.
Unlock the hasps and remove the cover from the GREEN MACHINE.
4.
Remove the two 45° flare tubing connections from the separator, being careful not to
damage the copper tubing.
5.
Remove the separator and while holding it vertically, gently shake it from side to side.
6.
If there is clearly excessive debris inside the separator, the separator must be replaced.
Figure 7-18: Separator Location