Project engineering CPU with integrated PROFIBUS DP master
For the project engineering of the PROFIBUS DP master you have to use
the hardware manager from Siemens. Your PROFIBUS projects are
transferred via MPI into the CPU 21x-2BM03 by means of the PLC
functions. The CPU passes the data on to the PROFIBUS DP master.
Note!
For the project engineering of the CPU and the PROFIBUS DP master a
thorough knowledge of the SIMATIC manager and the hardware configura-
tor from Siemens is required!
To be compatible to the Siemens SIMATIC manager, for the System 200V
the following steps are necessary:
•
Configure the CPU 315-2DP with the DP master system (address 2).
•
Add from the VIPA_21x.gsd the PROFIBUS slave "VIPA_CPU21x"
with
address 1.
•
Insert the CPU 21x-2BM03 at the 1. slot of the slave system.
•
Include the directly plugged peripheral modules at the sequencing slots.
•
Install the according GSD file for the slave system.
•
select from the hardware catalog the according slave system and drag it
to the master system.
•
Configure the according periphery modules of the slave system
•
Transfer the project to the CPU 21x-2BM03.
Overview
Fast introduction
Master-System
Slave system
Содержание System 200V Series
Страница 1: ...VIPA System 200V CPU Manual HB97E_CPU RE_21x 2BM03 Rev 14 44 October 2014 ...
Страница 4: ...Contents Manual VIPA System 200V ii HB97E CPU RE_21x 2BM03 Rev 14 44 ...
Страница 8: ...Safety information Manual VIPA System 200V 4 HB97E CPU RE_21x 2BM03 Rev 14 44 ...
Страница 66: ...Chapter 3 Deployment CPU 21x 2BM03 Manual VIPA System 200V 3 28 HB97E CPU RE_21x 2BM03 Rev 14 44 ...