100V Switching Module Field Wiring
Refer to the 100V Switching Module Installation Instructions (LT0668) for details on fitting and wiring this optional
module.
100V Splitter Module Field Wiring
Refer to the 100V Splitter Module Installation Instructions (LT0671) for details on fitting and wiring this optional module.
Expansion T-Gen2
Fit the expansion T-Gen2 as per the instructions in LT0667. Connect 24V from the master T-Gen2 to the expansion
T-Gen2 module, using red/black power wires.
Using the supplied RJ45 cable, connect the master T-Gen2 QBus OUT connector (J28) to the expansion T-Gen2 QBus
IN connector (J27).
Configure the expansion T-Gen2 with the Slave configuration and address 1 (refer to LT0667 for instructions).
Re-configure the master T-Gen2 to include a Slave T-Gen at address 1 using SmartConfig.
Paging
The BOWS can be configured for area paging using FP1117 100V Switching Modules and the Paging buttons on the
User Interface, or an external paging console. Refer to the T-Gen2 Installation & Wiring Instructions LT0667 for details.
PSU Rating
The BOWS is supplied with a 5A (FP1136) or 10A (FP1137) maximum current PSU. This limits the load that can be
connected to the T-Gen2 units, as AS 1670.1:2015 requires the PSU to be able to supply the full alarm load without any
batteries connected.
Figure 5 shows the 100V load that can be connected to the FP1136 BOWS with 1 and 2 T-Gen 60 units and varying
strobe currents.
Basically the FP1136 PSU can support:
1 x T-Gen 60 @ 60W load with up to 2A strobe load.
2 x T-Gen 60 @ 50W load each with no strobe load, decreasing to a combined 20W load with a total of 4A
strobe load.
Figure 5
– FP1136 T-Gen2 100V Load vs Strobe Current