Mounting the Solar-Divicon-HX
The discharge line of the pressure relief valve must lead
into a heat-resistant collecting tank with corresponding
size. The jug for the “Tyfocor-HTL“ solar fluid can be used
for this purpose. This allows you to easily refill the circuits
and to avoid undesired discharge into the environment!
1. Copy the holes to be drilled to the mounting
surface. The cardboard under the station may serve
as a template.
2. Drill the holes and insert the enclosed wall anchors.
3. Turn in the screws so that about 1“ of each screw
still sticks out.
4. Pull off the insulating front shell. Hang the station
onto the screws and tighten the screws.
5. Connect the transfer station to the system by
pipework:
»
1 supply from solar panel
»
2 return to solar panel
»
3 storage tank supply
»
4 storage tank return
All pipe connections are ¾“. The actual size of the
supply and return piping will vary depending on the type
and number of collectors used and the total length of the
pipe run. Please call Viessmann for sizing assistance.
1
2
3
4
Mounting
screw
locations
The location of installation must be dry, load-carrying and
frost-proof. Future access to the controller and the safety
equipment must be always guaranteed!
CAUTION
The mounting location must be able to carry the full
weight of the Solar-Divicon-HX. Take into account the
full weight of the unit. Damage or injury could occur if
not mounted securely.
Fig. 5 Pipe connections and mounting plate