If necessary, adjust the pre-mounted feet from 75 mm to 50 mm:
Pull the foot out and turn by 90°.
Attach urinal element to the floor using the fork spanner (size 13)
and the screws and dowels supplied.
Determine construction height in accordance with the on-site
marking of the upper edge of the finished floor.
Pull urinal element up (cutting check) and align.
x = Observe the instructions of the urinal manufacturer.
INFO! The construction height must be determined and
adhered to exactly.
There are only limited possibilities available to remedy errors
made during this assembly step,
.
Screw the urinal element together laterally with the support profiles.
75 mm
50 mm
13
x
x
1,0
m
0
0-2
00
mm
x
x
4x
4x
Handling
Viega Eco Plus urinal element siphon sensor technology
14 from 16