Rev. 8/2/2018
MEZZ-200, MANUAL
Copyright 2018 Vestil Manufacturing Co. Page 9 of 11
Assembling the Gate System:
At least 2 people should work together to assemble this gate system. Use the “Installation diagram” on page 8 to
determine how to orient the mezzanine gate system for your application. Numbers in parentheses () correspond to
item numbers in the parts lists on p. 4-7.
Step 1: Install the side gates (11). As shown in the
diagrams above and below, side gates should be 61
1
/
2
in.
apart (measured to inside edges of mounting brackets).
Secure the gates to the surface with
3
/
8
in. flat washers
and anchor bolts of appropriate length as determined by
your building engineer. Orient the gates so that the bolt
holes in the top rails are at the same end. The bolt holes
should also be opposite the edge of the mezzanine.
61
1
/
2
in.
69
1
/
2
in.
Step 2: Install the bottom gate (2) using
3
/
8
in. – 16 x
5in. bolts and the hardware indicated in the diagram
below.
(12)
(7)
(9)
(11)
(4)
(8)
Step 3: Connect the top gate to the bottom gate with
3
/
8
in. – 16 x
2
1
/
2
in. and related hardware as shown.
(6)
(8)
Step 4: Attach support braces with
3
/
8
in. – 16 x
2in. bolts (5), etc. Press plastic end caps (10)
(8)
(12)
(5)