Installation
Wiring
WARNING
Wiring of the device should only be performed by a licensed electrician. The circuit box’s main breaker
should be turned off to perform installation.
The insertion hole wire specification is AWG18 or Ø 1.02 (mm
²
).
The Clamp specification is 60A Ø10mm
Please make sure the main power in your facility is also off before installing. Follow the steps below:
1. Connect AC Input cable to a socket near the Electrical Box to power on the Clamp Meter.
2. Open the clamp as indicated by below picture. The clamp should be applied onto an electric cable The
arrow direction on the clamp need to point at the correct direction of the electricity current flows (
K
L
). If
arrow is faced in reverse direction, the reading will display negative value (-) however it will not influence
the readings.
3. Follow the schematics below as an example; clip the clamps on the electricity cables on the 2 the
incoming power cable connected to the Main Circuit Breaker.
Mounting
The Clamp Meter has a mounting bracket for mounting purposes.
1. Use the mounting bracket as template to mark the two holes on the wall for installing screws.
2. Screw the mounting bracket onto the wall according to marked location. Install wall plugs if necessary.
3. Locate the hooks of the mounting bracket and line up the hooks with the mounting holes on the Clamp
Meter. Fit the hooks into the mounting holes as picture below. Installation is now complete.
K
L