WIC On The Ground (Gravity) Foundation Kit Installation (P/N D1000-0000-0103)
This foundation kit is to be used on top of grade.
Grade Considerations
1.
Ground/gravel should be normally dry and have good drainage.
2.
Ground/gravel should be level or very close.
WIC On The Ground (Gravity) Foundation Kit Installation Procedure
1.
Lift and set the WIC On The Ground (Gravity) Foundation Kit in the desired location. The WIC On The
Ground (Gravity) Foundation Kit ships assembled, stairs separate of course, so lift and set it on grade in
desired location. If using a forklift and the forks are not long enough to get under all three bars of the
frame, make sure the frame does not tilt over during lifting. This can be accomplished with weight on
the two bars the forks did get under, or by removing the footers from the bar the forks did not get under.
This is aimed at safety as the frame can withstand tilting. The weight of the frame is 300lbs. The weight
of the footers are 31lbs each. See
Figure 24:
Gravity Mount Foundation Kit
2.
Level the frame by adjusting the leveling hardware between the frame and the nine footers. Be sure to
maintain 18 inches from grade to the top of the frame, which is the bottom of the WIC. Start by leveling
the four corners first then adjust the remaining footers.
3.
Lift and set the WIC on the WIC On The Ground (Gravity) Foundation Kit in desired location. Be sure to
bolt the WIC base to the frame prior to releasing all of the weight of the WIC on the frame. See “WIC
Lifting and Placement Procedures” starting on page 77.
4.
Once all hardware is installed connecting the WIC base to the frame, tighten and secure the hardware.
5.
Install the WIC stairs using the provided hardware.