26 Chapter 3 Installation
NetSure 801 CA7 Power Supply System (New Skelecton) User Manual
Chapter 3 Installation
This chapter introduces installation and cable connection.
3.1 Installing Cabinet
3.1.1 Installation On The Floor
Step 1: mark the installation position
Determine the installation position of the power supply cabinet in the equipment room according to the installation
drawing. Based on the mechanical parameters (see Figure 3-1) of the installation holes of the power supply cabinet,
determine the exact position of the center points of the installation holes on the floor, and mark them with a pencil or
oil pen.
370
600
600
436
4- 18
600
4
0
0
6
0
0
4-
Ф
18
800
(a) Installation size of the rectifier cabinet (b) Installation size of the AC/DC distribution cabinet
Figure 3-1 Installation size of the cabinet base (unit: mm)
Step 2: drill reserve holes
The expansive pipes delivered along with the system are generally M10 × 65mm. Therefore, use electric drill with drill
bit Φ14 to drill holes at the center points of the installation holes marked on the floor, and the depth of the holes
should be 70mm. To avoid being off-center, be careful not to shake the drill, and try to keep it as vertical as possible
to the floor.
Step 3: install expansive pipes
Clean the dust, and insert the expansive pipe into the reserve hole, knock it down gently using a hammer until the top
of the expansive pipe is level with the ground.
Step 4: place cabinet in position
Move the cabinet to the installation position aligning the installation holes of the cabinet with the reserve holes on the
ground.