Vertiv™ Liebert EXS 80kVA UPS User Manual
5 UPS Operating Instructions
Figure 5-1 UPS power switch
Cold start
button
Q1
Q2
Q3
Q5
5.1.3. Check before Start-up
1.
Check and confirm that the UPS power distribution mode is correct, that the power cables and signal
cables are connected correctly, and there are no short circuits.
2. Check that the batteries have been installed properly, the cables have been connected correctly, and
that the positive and negative battery poles are correct.
3. Measure the mains voltage and frequency, and verify that they are correct.
4. The UPS output terminals are energized when the UPS is switched on. If the load has been already
connected to the output terminals, make sure that it is safe to apply power to it.
Important! The user may only switch the UPS on once the UPS has been installed completely
and the authorized service engineer has completed the commissioning tests and shut down the
external power input switches.
5.2 UPS Start-up Procedures
The UPS must be completely installed and tested by authorized engineer, and external power supply
switch is closed, then you can start the UPS.
Содержание Liebert EXS 80kVA UPS
Страница 1: ...Liebert EXS 80kVA UPS User Manual...
Страница 8: ...vi Vertiv Liebert EXS 80kVA UPS User Manual This page is intentionally left blank...
Страница 12: ...4 Vertiv Liebert EXS 80kVA UPS User Manual Safety Precaution This page is intentionally left blank...
Страница 24: ...16 Vertiv Liebert EXS 80kVA UPS User Manual 1 Overview This page is intentionally left blank...
Страница 34: ...26 Vertiv Liebert EXS 80kVA UPS User Manual 2 This page is intentionally left blank...
Страница 94: ...86 Vertiv Liebert EXS 80kVA UPS User Manual 7 This page is intentionally left blank...
Страница 110: ...102 Vertiv Liebert EXS 80kVA UPS User Manual 10 This page is intentionally left blank...
Страница 119: ...111 Vertiv Liebert EXS 80kVA UPS User Manual...