5 ELECTRICAL FIELD CONNECTIONS
Three-phase electrical service is required for all models. Electrical service must conform to national and local electrical
codes. Refer to equipment nameplate regarding wire size and circuit protection requirements. Refer to the appropriate
submittal drawing, listed in Table 5.1 on the next page, for electrical service entrances into unit
A manual electrical disconnect switch should be installed in accordance with local codes and distribution system. Consult
local codes for external disconnect requirements.
WARNING! Arc flash and electric shock hazard. Open all local and remote electric power-supply disconnect
switches, verify with a voltmeter that power is Off and wear appropriate, OSHA-approved personal protective
equipment (PPE) per NFPA 70E before working within the electric control enclosure. Failure to comply can
cause serious injury or death. Customer must provide earth ground to unit, per NEC, CEC and local codes, as
applicable. Before proceeding with installation, read all instructions, verify that all the parts are included and
check the nameplate to be sure the voltage matches available utility power. The Liebert® controller does not
isolate power from the unit, even in the “Unit Off” mode. Some internal components require and receive
power even during the “Unit Off” mode of the controller. The factory-supplied disconnect switch is on the
exterior of the enclosure. The factory-supplied, optional disconnect switch is inside the unit. The line side of
this switch contains live high-voltage. The only way to ensure that there is NO voltage inside the unit is to
install and open a remote disconnect switch. Refer to unit electrical schematic. Follow all local codes.
WARNING! Risk of electric shock. Can cause equipment damage, injury or death. Open all local and remote
electric power supply disconnect switches and verify with a voltmeter that power is off before working within
any electric connection enclosures. Service and maintenance work must be performed only by properly
trained and qualified personnel and in accordance with applicable regulations and manufacturers’
specifications. Opening or removing the covers to any equipment may expose personnel to lethal voltages
within the unit even when it is apparently not operating and the input wiring is disconnected from the
electrical source.
WARNING! Risk of improper wire sizing/rating and loose electrical connections. Can cause overheated wire
and electrical connection terminals resulting in smoke, fire, equipment and building damage, injury or death.
Use correctly sized copper wire only and verify that all electrical connections are tight before turning power
On. Check all electrical connections periodically and tighten as necessary.
WARNING! Risk of wiring damage, short circuits and electric shock. Can cause overheated wiring, smoke, fire,
activation of fire suppression systems and EMS personnel and equipment, building and equipment damage,
injury or death. Insert CSA certified or UL listed bushings into holes and or knockouts used to route wiring
through metal panels to protect the wire insulation from contact with sheet metal edges.
5 Electrical Field Connections
21
Содержание Liebert DSE Packaged 400
Страница 1: ...Liebert DSE Packaged Solution Installer User Guide 400 kW to 500 kW...
Страница 24: ...Vertiv DSE Packaged Solution Installer User Guide 20 This page intentionally left blank...
Страница 32: ...Vertiv DSE Packaged Solution Installer User Guide 28 This page intentionally left blank...
Страница 34: ...Vertiv DSE Packaged Solution Installer User Guide 30 This page intentionally left blank...
Страница 36: ...Vertiv DSE Packaged Solution Installer User Guide 32 This page intentionally left blank...
Страница 68: ...Vertiv DSE Packaged Solution Installer User Guide 64 This page intentionally left blank...
Страница 103: ...Vertiv DSE Packaged Solution Installer User Guide 66 This page intentionally left blank...
Страница 104: ...Vertiv DSE Packaged Solution Installer User Guide...