6. Position the DCF in the installation location using the forklift, with 2 or more people carrying it,
or by rolling the rack on its casters.
•
If using the casters to move the rack, raise the leveling feet before moving.
7. Position the rack and do one of the following:
•
Lower the leveling feet
•
Bolt the rack to the floor with the shipping/anchoring brackets.
Figure 4.1 Removing rack from shipping pallet
ITEM
DESCRIPTION
1
Anchor bracket
2
Bolt-hole for securing anchor bracket to rack (2 typical)
3
Lag-bolt holes for securing anchor bracket to pallet and/or floor
4.4 Equipment Layout, Repositioning, Removal and Installation
To keep the unit’s center of gravity as low as possible, install equipment from the bottom up, starting with
the heavier units. Leave any unused space at the top of the rack.
CAUTION: After equipment is installed, the DCF Optimized Rack System may have a high center of
gravity. Avoid tipping the unit when it is being moved.
4.4.1 Installing the Edge Guard
1. Press edge guard to the top-cover cut outs by pressing along the edge of the cut out opening
as shown in the following figure.
Vertiv
| DCF Installer/User Guide |
14
Содержание DCF 42U
Страница 1: ...DCF Optimized Rack System Installer User Guide...
Страница 4: ...Vertiv DCF Installer User Guide 4...
Страница 6: ...Vertiv DCF Installer User Guide 6 This page intentionally left blank...
Страница 8: ...Vertiv DCF Installer User Guide 8 This page intentionally left blank...
Страница 12: ...Vertiv DCF Installer User Guide 12 This page intentionally left blank...
Страница 22: ...Vertiv DCF Installer User Guide 22 This page intentionally left blank...
Страница 23: ......