ITEM

DESCRIPTION

5

Depth-adjustable interior bracket

6

Foam gasket

7

Right-rear EIA rail

8

Air-intake baffle

9

Right-front EIA rail

10

Foam gasket

11

Front of enclosure

12

Left-front EIA rail

13

Air-exhaust baffle

To install the baffle, finger cable managers, and cover plates:

1. Insert one side of the baffle through the front or rear of the rack, and set it on top of the

bottom-gusset of the EIA rail.

2. Mate the side of the baffle to the side of the EIA rail, align the cutouts, and secure to the front

and rear rails with the fasteners as shown in the following figure.

3. Repeat steps 1 and 2 for the second side of the baffle.
4. Install the brush strip onto flange of the depth-adjustable interior bracket.
5. Peel the backing from the foam gasket, and stick it in place on the top and bottom flanges of

the baffle. You may need to cut the gasket to size.

Figure 4.11 Fastening the baffle to the rail

ITEM

DESCRIPTION

1

EIA rail gusset

2

M6 carriage bolt

Vertiv

| DCE Installer/User Guide |

34

Содержание DCE 42811

Страница 1: ...DCE Rack System Installer User Guide...

Страница 2: ...any installation or operational issues with your product check the pertinent section of this manual to see if the issue can be resolved by following outlined procedures For additional assistance visi...

Страница 3: ...ssories 23 4 1 Vertical Cable Manager Kit E846015 23 4 2 Horizontal Front to rear Cable Manager E11015 E12015 25 4 3 Front to rear Cable Trough E811015 E812015 25 4 4 Adjustable Ladder rack Bracket EL...

Страница 4: ...Vertiv DCEInstaller User Guide 4...

Страница 5: ...ce personnel Do not attempt to move racks by yourself WARNING All wiring and electrical circuits must be in compliance with National and Local electric codes Only ITE Information Technology Equipment...

Страница 6: ...Vertiv DCEInstaller User Guide 6 This page intentionally left blank...

Страница 7: ...1100 E42612 42 600 1200 E426112DR 42 600 1100 E42711 42 700 1100 E42712 42 700 1200 E42811 42 800 1100 E42812 42 800 1200 E42112 42 1000 1200 E45611 45 600 1100 E45612 45 600 1200 E45711 45 700 1100...

Страница 8: ...Vertiv DCEInstaller User Guide 8 This page intentionally left blank...

Страница 9: ...apacity for the DCE Rack is 3000 pounds on the floor or on leveling glides To maintain a uniform distribution of the mechanical load in the DCE Rack load the heaviest equipment first at the bottom of...

Страница 10: ...iding downward into door and tilting inward 5 Re install swing handle retainer and Phillips head bolt Figure 3 1 Door handle components ITEM DESCRIPTION 1 Phillips head bolt 2 Phillips head cam retain...

Страница 11: ...onnected 1 Open the door beyond 90 then pull on the hinge pins 2 Carefully pull the door away from the rack to detach the door 3 To attach the door align the hinges and slide hinge pins back into the...

Страница 12: ...mer top right hinge at the bottom left and the former bottom right hinge at the top left with the open end of the hinge facing the outside of the rack Using a T30 screwdriver remove and re install the...

Страница 13: ...ll the side panel Reverse the process and lock the panel Make sure the slots on the side panel engage with the two tabs at the bottom of the frame 3 8 Top Panel Mounting The top panel of the rack is i...

Страница 14: ...gh from the top panel 2 On the top panel remove the 6 M6 flat head Torx screws and lift the top panel out or off To install the top panel 1 Insert the top panel and fasten with 6 M6 FH Torx screws 2 R...

Страница 15: ...panel CAUTION Risk of sharp edges The edges of the cutouts are sharp Be careful when removing the fasteners 4 At the front of the rack starting with the left panel lift the center of the panel up and...

Страница 16: ...reduce the weight of the rack To field install casters 1 Tip the rack over and lay it on its side NOTE Be sure to install swivel casters on the front and fixed casters on the rear of the rack 2 Instal...

Страница 17: ...swivel casters on front of rack ITEM DESCRIPTION 1 Swivel caster assembly 2 M8 keps nut 3 M8 pem studs 4 Side of frame 5 Leveling foot 6 Front of rack 7 M8 bolt 8 M6 nut 9 M6 carriage bolt Vertiv DCEI...

Страница 18: ...e 3 8 Attaching support bar between casters ITEM DESCRIPTION 1 M8 pem studs 2 M8 keps nuts 6 Install the fixed casters on the rear of the rack as shown in the following figure Align the holes in the c...

Страница 19: ...ach the support bar that connects the two casters Align the holes on the end of the support beam with the M8 pem studs on the caster assembly Using a 13 mm socket secure with M8 keps nut and tighten t...

Страница 20: ...2 Mounting Rail Adjustment Each rack has two pairs 12 ga steel powder coated vertical mounting rails installed with all standard frames at 19 in EIA 310 E Universal cage nut rails M6 are standard Rack...

Страница 21: ...e horizontal support Figure 3 11 Rail features and hardware ITEM DESCRIPTION 1 Vertical mounting rail 2 Lobster claw holes 3 Cable pass through cut outs 4 Cable tie down slots 5 Accessory mounting hol...

Страница 22: ...tally using the M6 keps nuts and screws as shown in the figure WARNING When using power distribution units PDUs each PDU should be connected to a dedicated branch circuit that is rated for the continu...

Страница 23: ...m the front of the rack When stalled in 700 mm and 800 mm wide racks the vertical cable manger kit does not require AMH adapter brackets When installed in in 600 mm wide racks AMH adapter brackets are...

Страница 24: ...with Brush Kit and Vertical Cable Manager on page 32 Figure 4 1 Installing cable management kit including detail of AMH bracket installation ITEM DESCRIPTION 1 AMH adapter bracket 2 Tabs for out put p...

Страница 25: ...1 M6 Hex head bolt 2 Hex nut 3 Mounting rail 4 Lacing bar 4 3 Front to rear Cable Trough E811015 E812015 The 800 mm wide racks with depths of 1100 mm and 1200 mm have the option for front to rear cabl...

Страница 26: ...A rail holes 6 Outer trough assembly 7 Inner trough assembly 8 Screws for tab holes in EIA rail holes 9 Center screws 4 4 Adjustable Ladder rack Bracket ELRB016 The adjustable ladder rack and basket t...

Страница 27: ...reference only 2 J bolt 3 1 4 20 Hex nut 4 M6 Hex head bolt 5 M6 cage nut 6 Square holes for M6 cage nuts 7 5 16 18 Hex nut 8 5 16 flat washer 9 1 4 20 carriage bolt 10 Adjust top section to final hei...

Страница 28: ...00 mm racks use DCE6016 700 mm racks use DCE7016 800 mm racks use DCE8016 To install the overhead cable trough 1 Place the trough where you require cable routing 2 Insert a cage nut into the appropria...

Страница 29: ...When the chimney is at the desired height use a screwdriver to punch out the appropriate knockout along each side of the chimney 3 Insert the chimney knob into the knockout to secure the chimney Figu...

Страница 30: ...r first AMH on all racks 2 Tool less rivets for 1 4 in push holes 3 Brush grommet strips 4 RU break off intervals on brush strip mounting plate for 45 RU and 42 RU racks 5 Top view of brush grommet in...

Страница 31: ...stalls using the accessory mounting holes AMH along the rail Figure 4 8 700 mm baffle components and grommet installation ITEM DESCRIPTION 1 Top cross plate for first AMH on all racks 2 Tool less rive...

Страница 32: ...nt of the rack When installing both options place a vertical cable manager on top of the mounting plate of the vertical airflow baffle align with the AMH Insert a tool less rivet through both the vert...

Страница 33: ...baffle 24 cover panels for EIA rails with fasteners Cable management rail kit with 12 finger managers and fasteners The switch kit controls air flow for proper switch performance The following figure...

Страница 34: ...EIA rail 2 Mate the side of the baffle to the side of the EIA rail align the cutouts and secure to the front and rear rails with the fasteners as shown in the following figure 3 Repeat steps 1 and 2...

Страница 35: ...IPTION 1 Top plate baffle 2 10 flat washer 3 10 32 PH pan head screw 4 Finger cable management section 5 10 32 Keps nut 7 Install the cover plates as shown in the following figure example of front sho...

Страница 36: ...switch E9513014 Kit for 14 RU Cisco switch E6513014 Kit for 19 RU Cisco switch To install the baffles 1 Make sure to orient the baffles for proper air flow as follows Place the left side exhaust baffl...

Страница 37: ...riage bolts and wing nuts in the square holes above and below each tab to secure the baffle to the rails Figure 4 14 Switch baffle installation for 800 mm rack ITEM DESCRIPTION 1 Exhaust baffle 2 Gask...

Страница 38: ...cold aisle best practices The gasket must be installed before baying racks To install the gasket 1 Measure and cut gasket to length 2 peel adhesive backing from the gasket and place the gasket around...

Страница 39: ...4 in or 600 mm which determines the screw holes used in the bracket see the following figure 3 Install 2 brackets at front and 2 at rear per the rack s mating planes as shown in the figure Figure 4 16...

Страница 40: ...Vertiv DCEInstaller User Guide 40 This page intentionally left blank...

Страница 41: ......

Страница 42: ...logos referred to are trade names trademarks or registered trademarks of their respective owners While every precaution has been taken to ensure accuracyand completeness herein Vertiv Co assumes no r...

Отзывы: