STEP 5: INSTALL THE NODE
5.1
5.4
5.2
5.5
5.3
Verify that the outer rail is securely
attached to the rack. Pull the intermediate
rail forward. Ensure that the ball bearing
retainer is locked forward.
Verify that the inner rail is securely
attached to the node. Align the inner rail
of the node to the intermediate rail in the
rack. Slide the node forward into the rack.
The rail has a lock mechanism that prevents
the hardware from being fully pushed into the
rack. Pull the blue tab forward to unlock the
intermediate rail and continue sliding the node
into the rack.
Angle in the right side of the bezel so that
the upper and lower tabs on the right side
engage with the corresponding holes
on the chassis. Rotate the key counter-
clockwise until it stops, which is past the
“lock”
icon in the 11 o’clock position
Secure the captive screws onto the
node ears.
Copyright© 2022 Veritas Technologies LLC. All rights reserved.
Once you have installed the
storage shelves, node rack
rails, and node, refer to the
cabling guide to connect