VALSTEAM ADCA ADCAMAT POP Скачать руководство пользователя страница 1

 

       

 

          

     

ADCA

 

                            

 

VAL

S

TEAM

 

ADCA

                     

 

 

 

IMI 9.101 E 02.17 

INSTALLATION AND MAINTENANCE INSTRUCTIONS 

ADCAMAT POP 

– PPO-14 – PPA-14 PRESSURE OPERATED PUMPS  

 

GENERAL 
 

 

These  instructions  must  be  carefully  read  before  any  work  involving  products  supplied  by  VALSTEAM  ADCA 
ENGINEERING S.A. is undertaken. 

 

 

The  installation  procedure  is  a  critical  stage  in  a  life  of  the  equipment  and  care  should  be  taken  to  avoid 
damage to the equipment. 

 

 

They  give  their  maximum  performance  only  when  the  equipment  associated  with  them  is  correctly  sized  and 
installed in accordance with our recommendations. 

 

 

The POP pumps are designed for condensate pumping, cold water and other group 2 fluids, without the use of 
electricity.  They  are  specially  recommended  to  return  high  temperature  condensate  back  to  boiler  houses  to 
save and conserve energy. 

 

 

The  ADCAmat  automatic  pumps  can  lift  hot  condensate,  oils  and  other  liquids  as  high  as  60m  (200ft)  or 
discharge  against  an  equivalent  total  back  pressure.  The  pump  starts  when  there  is  something  to  pump  and 
stops when there isn’t. 

 

 

Liquid  flows  by  gravity  into  the  pump  through  an  inlet  check  valve  lifting  a  float  which  at  the  upper  limit  of  its 
travel  opens the supply  valve  which  allows steam or compressed air to enter the pump body.  Pressure  in  the 
pump  builds  up  until  just  sufficient  to  overcome  back  pressure.  The  pressurized  liquid  opens  the  outlet  check 
valve  and  discharge  commences.  When  the  float  reaches  the  minimum  lower  level,  it  closes  the  steam  or 
compressed air supply valve and opens the vent allowing the liquid to fill the pump again, beginning other cycle. 

 
 

Note: 
 

 

Current regional safety regulations should be taken in to account and followed, while doing the installation and 
maintenance work. 

 

Handling, installation and maintenance work must be carried out by trained personnel. A supervisor must follow 
and check all activities. 

 

For  the  problems  that  cannot  be  solve  with  the  help  of  this  instructions,  please  contact  the  supplier  or  the 
manufacturer. 

 

The manufacturer reserves the right to change the design and material of this product without notice. 

 

If  necessary  to  perform  hydrostatic  test  on  the  equipment/installation  be  aware  of  the  limits  according  to  the 
table below. The internal mechanism cannot be subject to the hydrostatic test of the body. 

 

 

 

 
 
 
 
 
 
 

 
 

 

 

 
 
 
 
 

 

 

Press.      

bar

Tem p.      

ºC

Press.      

bar

Tem p.      

ºC

16

50

16

50

14

100

16

100

13

195

13

195

12

250

12

250

16

50

16

50

13

195

13

195

Minimum operation temp. : -10ºC; Design code: ASME VIII

* Rating according to  EN1092:2007

LIMITING CONDITIONS*

ANSI 

Cl.150

PN16

PN16

ANSI 

Cl.150

POP-S/PPO-14S/PPA-14S

POP-SS/PPO-14SS/PPA-14SS

RATING

POP-S/PPO-14S/PPA-14S

POP-SS/PPO-14SS/PPA14SS

PN 16

23 bar

26 bar

Note: The internal mechanism cannot be subject to the hydrostatic test of the body

PRESSURE TEST [bar] 20ºC

Содержание ADCAMAT POP

Страница 1: ...ust sufficient to overcome back pressure The pressurized liquid opens the outlet check valve and discharge commences When the float reaches the minimum lower level it closes the steam or compressed ai...

Страница 2: ...ng temperature and pressure limits laid down for them otherwise they may fail refer to nameplate and or IS Information Sheet Manual handling of products may present a risk of injury You are advised to...

Страница 3: ...e to inappropriate handling during the transportation and storage See figure below for correct position in transportation Incorrect position Correct position INSTALLATION Account for over pressure con...

Страница 4: ...ctly Ensure that the unit is leveled for proper operation External stresses that may be induced by the system due to pipe expansion etc can affect this product The necessary precautions are recommende...

Страница 5: ...te the maintenance work 4 Replace and tighten the connections Don t forget to substitute the gasket 5 Consider the start up conditions TROUBLESHOOTING If the malfunctions cannot be solved with the hel...

Страница 6: ...FLOAT AND GASKET 80 3 7 1 Set A 95 5500 225 PPA 14 SPRING SET 80 8 1 Set A 95 5500 325 PPA 14 COVER GASKET 80 3 1 Set A 61 1140 025A INLET ADCAMAT NON RETURN VALVE 25 9 2 1 A 61 1140 040A INLET ADCAMA...

Страница 7: ...ADCA VALSTEAM ADCA IMI 9 101 E 02 17 PPA 14 PPO 14...

Страница 8: ...y calibrated from the factory Do not unscrew the nuts Nr 17A and 19A 3 After replacing the valves and support make sure that the mechanism is working correctly by manually operating the float POP S DN...

Страница 9: ...80 1 Tighten up screw nr 18C increase lower level 2 Untighten the screw nr 18C decrease lower level How to replace Inlet Outlet valves on PPA 14 1 With the float at the lowest position remove the bolt...

Страница 10: ...on PRODUCTS RETURNING Information regarding any hazards and precautions to be considered because of contaminating fluids and residues or mechanical damage that may represent a health safety or environ...

Отзывы: