Citysphere S
Preparation for installation
5
2. Preparation for installation
2.1. Safety instructions
•
The safety instructions outlined on pages 3 and 4 must be read
and noted before starting work.
•
Installation should be performed by someone well versed in auto
mechanics/auto electrics.
2.2. Conditions for assembly
•
Before assembling and operating the air-conditioning system(s),
the vehicle's power supply must be checked for sufficient capacity,
and must be upgraded if necessary.
•
A free generator capacity of 65 A (max. current consumption per
unit) must be at disposal per unit to be constructed. This capacity
must be guaranteed at idle speed, and at the same time at
maximum engine compartment temperature (low speed and high
ambient temperature diminish the output of generators).
2.3. Preparations on vehicle’s roof
When working on the bus roof or on any hoisting equipment,
scaffolding etc. suitable safety precautions must be taken to
prevent falls.
Wear protective gloves!
2.4. Roof cut-outs
The required roof cut-outs (opening for refrigerant connection and
electrical interfacing) must be clearly indicated on the roof. Make
the roof cut-out using suitable tools. Cut edges should be deburred
and protected against corrosion.
NOTE:
Interface drawings can be obtained from Spheros!
Warning!
Danger of severe injuries or
fatal fall!
Caution!
Danger of cut injuries due to
sharp metal edges!