Please verify correct installation of your Hyland 920 Wind Turbine using the checklist below..
Commissioning
Hyland 920 Commissioning Chart
Completed
Page
TOWER
Installed as per manufacturer’s instructions
Turbine Plumbed vertical
ELECTRICAL SYSTEM
20A breaker installed between controller and
power system
10 AWG wires installed between controller
and power system/ battery
HYLAND 920
Yaw clamp tightened to 4 Nm
Turbine is tracking wind (tower vertical)